MahaRERA Property Intelligence · Mumbai City

Ram Setu Bhavan

P51900055203 · MATUNGA DIVISION,DADAR EAST · promoter Gbd Infracon Llp

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationP51900055203
Registered on11 Mar 2024
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Gbd Infracon Llp is the promoter of record on 189 projects, of which 18 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~45.7% of the estimated project cost incurred as of the last certificate (₹33.51 Cr spent against a ₹73.40 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 24 homes filed with MahaRERA, 7 are sold/booked (3 with registered agreements + 4 booked) and 17 remain available (~29% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹19.71 Cr in agreement value so far. Of that, ₹7.18 Cr (~36%) is already collected, ₹12.52 Cr receivable — a read on how far along these sales really are. Note: the project registers 59 homes in total, but this sold/unsold inventory filing covers only 24 of them — the other 35 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 7 registered agreements, the effective carpet rate is ₹34,207/sqft (typical range ₹28,529–₹74,400) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 13527 sqft (48.93 sqm)₹98.73 Lakh
Floor 121201769 sqft (71.48 sqm)₹1.59 Cr
Floor 121204769 sqft (71.48 sqm)₹1.59 Cr
Floor 131301769 sqft (71.48 sqm)₹1.59 Cr
Floor 1313021,146 sqft (106.45 sqm)₹2.36 Cr
Floor 131304769 sqft (71.48 sqm)₹1.59 Cr
Floor 141401769 sqft (71.48 sqm)₹1.59 Cr
Floor 151501769 sqft (71.48 sqm)₹1.59 Cr
Floor 161604769 sqft (71.48 sqm)₹1.59 Cr
Floor 1818021,106 sqft (102.74 sqm)₹2.28 Cr
Floor 191901769 sqft (71.48 sqm)₹1.59 Cr
Floor 1919031,007 sqft (93.58 sqm)₹2.08 Cr
Floor 191904769 sqft (71.48 sqm)₹1.59 Cr
Floor 202001769 sqft (71.48 sqm)₹1.59 Cr
Floor 2020021,106 sqft (102.74 sqm)₹2.28 Cr
Floor 2020031,007 sqft (93.58 sqm)₹2.08 Cr
Floor 9904567 sqft (52.64 sqm)₹1.12 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+26 and 59 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ram setu bhavan1G+2659-

Unit mix on the filing: 46 residential and 13 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MATUNGA DIVISION,DADAR EAST, JUNCTION OF KATRAK AND TILAK ROAD, Mumbai City, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by BEST, to the south by TILAK ROAD, to the east by KATRAK ROAD and to the west by BEST. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~8173 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort8171 km
Lower Parel / Worli business district8173 km
Chhatrapati Shivaji Int'l Airport8177 km
Bandra Kurla Complex (BKC)8178 km
Andheri MIDC / SEEPZ8178 km
Powai / Hiranandani business park8182 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Bhalchandra Niwas CHS
possession by Dec 2026 · Ishaan Realtors
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD

Other RERA-registered projects in Mumbai City

Raman Tara Heights
declared completion Dec 2017 · Surendra Mody AND Others
Ramkunj
declared completion Dec 2021 · Silver Arch Builders & Promoters
Ramkunj
declared completion Dec 2025 · Jayant Jagannath Sirsat
Ramswaroop Palai Tower
declared completion Jun 2023 · Dhanji Gelabhai Gala
Ranka Lifestyle Ventures
declared completion Jun 2023 · Bhavesh Jayantilal Jain
Ratan Address
declared completion Mar 2026 · Shri Nakoda Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026