RATI COASTALBAY

PR1270002502348 · Sector No. 10B · promoter Rati Realty And

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationPR1270002502348
Registered on13 Feb 2026
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Construction Progress

MahaRERA's cost filing puts construction at ~37.9% of the estimated project cost incurred as of the last certificate (₹1.22 Cr spent against a ₹3.22 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 14 homes filed with MahaRERA, 0 are sold/booked and 14 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101482 sqft (44.82 sqm)₹44.37 Lakh
Floor 1102482 sqft (44.82 sqm)₹44.37 Lakh
Floor 2201482 sqft (44.82 sqm)₹44.37 Lakh
Floor 2202482 sqft (44.82 sqm)₹44.37 Lakh
Floor 3301482 sqft (44.82 sqm)₹44.37 Lakh
Floor 3302482 sqft (44.82 sqm)₹44.37 Lakh
Floor 4401482 sqft (44.82 sqm)₹44.37 Lakh
Floor 4402482 sqft (44.82 sqm)₹44.37 Lakh
Floor 5501482 sqft (44.82 sqm)₹44.37 Lakh
Floor 5502482 sqft (44.82 sqm)₹44.37 Lakh
Floor 6601482 sqft (44.82 sqm)₹44.37 Lakh
Floor 6602426 sqft (39.58 sqm)₹39.18 Lakh
Floor 7701457 sqft (42.45 sqm)₹42.03 Lakh
Floor 7702401 sqft (37.22 sqm)₹36.85 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 14 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RATI COASTALBAY - BUILDING - 21G+714-

Unit mix on the filing: 14 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Sector No. 10B, situated at 15.00 Mtr Wide Road, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by -, to the south by -, to the east by - and to the west by -. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~19 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district19 km
Powai / Hiranandani business park20 km
Nariman Point / Fort20 km
Chhatrapati Shivaji Int'l Airport21 km
Andheri MIDC / SEEPZ23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Rati Omkara
possession by Dec 2026 · Rati Builders AND Developers
Rati Vighnarta
declared completion Dec 2025 · Rati Builders AND Developers
Ratnamisha Villas
possession by Dec 2028 · Khushy Jeevan Builders LLP
Ravechi Complex
declared completion Jun 2018 · Live Enterprises
Ravechi Deep
declared completion Sep 2019 · Smit Kiran Doshi
Ravechi Height
declared completion Feb 2024 · Bhaveshwar Corporation

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026