Mumbai/Project record

MahaRERA · the public record

REDEVELOPMENT OF NEW SHALIMAR APARTMENTS CHSL

MUMBAI · PRANAV CONSTRUCTIONS LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800034915

Delivery and registration

When is the project declared for completion?

REDEVELOPMENT OF NEW SHALIMAR APARTMENTS CHSL is registered with MahaRERA as P51800034915 and the promoter has declared completion for 30 Sep 2025.

30 Sep 2025

declared completion

12months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800034915
Registered on28 Apr 2022
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 12 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for REDEVELOPMENT OF NEW SHALIMAR APARTMENTS CHSL record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Pranav Constructions Limited is the promoter of record on 64 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

64projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for REDEVELOPMENT OF NEW SHALIMAR APARTMENTS CHSL in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
NEW SHALIMAR APARTMENTS CHSL1G+1030 Sep 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MUMBAI , BUILDING NO 4 JANKALYAN NAGAR KHARODI MALAD WEST, Borivali, Mumbai Suburban, 400095. Per the filed land record, the plot is bounded to the north by CTS NO 6, to the south by MUNICIPAL ROAD VIDE CTS NO 9 11, to the east by CTS NO 9 8 and to the west by CTS NO 9 6. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pranav Constructions Limited is the promoter on 47 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Pranav Constructions Limited project & its RERA track record →

Other flagged projects by Pranav Constructions Limited

Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Malad West

95 West Composite
possession by Dec 2026 · Stans Buildtech Realty
BAY VUE
possession by Dec 2026 · H AND Y Realities Private Limited
Galaxy Heights Tower 1
possession by Dec 2026 · Maharashtra Police Cooperative Housing F
Lotus
possession by Dec 2026 · Rajeshwar Land Developers Private Limite
Royal Lagoon E Wing
possession by Dec 2026 · Rikki Ronie Developers
Royal Lagoon F Wing
possession by Dec 2026 · Rikki Ronie Developers

Other RERA-registered projects in Mumbai Suburban

Redevelopment Of Nirav Chsl
declared completion Dec 2024 · Navin Karamshi Shah
Redevelopment Of OB Swarganga Chsl CTS No 154 Pt Survey No 383 Pt Chaitanya Ngr Santacruz E Mum 55
declared completion Dec 2021 · A A Estates Pvt Ltd
Redevelopment OF OM Manikanta Chsl
possession by Dec 2027 · Pranav Constructions Limited
Redevelopment Of Parvatikunj Chsl
declared completion Dec 2023 · Yash Om Developers
Redevelopment OF Pearl Palace
possession by Sep 2027 · Pranav Constructions Limited
Redevelopment OF Plot NO. 212
declared completion Feb 2025 · Pranav Constructions Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026