Mumbai/Project record

MahaRERA · the public record

Redevelopment of Prateeksha CHS Ltd

Eksar Villag, Babhai · ASHIANA ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800016261

Delivery and registration

When is the project declared for completion?

Redevelopment of Prateeksha CHS Ltd is registered with MahaRERA as P51800016261 and the promoter has declared completion for 30 Sep 2018.

30 Sep 2018

declared completion

96months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800016261
Registered on02 May 2018
Promoter-declared completion30 Sep 2018
Current statusCertificate Signed
Against todayabout 96 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Redevelopment of Prateeksha CHS Ltd record 2 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ashiana Housing is the promoter of record on 18 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

18projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Redevelopment of Prateeksha CHS Ltd in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Redvp of Prateeksha CHS Ltd1G+830 Sep 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2019Respected Sir, Our project named of Prateeksha C.H.S. Ltd. CTS No. Bearing F.P.No.254,Off TPS III, on 51st Road, Borivali, Mumbai-400092. Is delayed because of necessary sanctions

Location, Land & Connectivity

Located at Eksar Villag, Babhai , -, Andheri, Mumbai Suburban, 400091. Per the filed land record, the plot is bounded to the north by By Internal Road leasing to public Road, to the south by Partly by F Plot No 267 andPartly By F Plot No 266, to the east by Final Plot No 255 and to the west by Final Plot No 253. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every Ashiana Enterprises project & its RERA track record →

Other RERA-registered projects in Borivali West

Bhoomi Pratishtha
possession by Oct 2026 · Bhoomi Shashwat Estate Pvt. Ltd.
Bank OF India Employees Sukhada Chsl
possession by Dec 2026 · M/S Hirani Realtors
Jaykant Bliss
possession by Dec 2026 · Chitalia Builders
Gagansagar
possession by Dec 2026 · HUM Developers Private Limited
Empire Meghna
possession by Mar 2027 · Empire Realty
Goyal Nrupa Square
possession by Mar 2027 · Parshwa Amrit

Other RERA-registered projects in Mumbai Suburban

Redevelopment OF Rajesh Mandir Chsl
possession by Jul 2028 · Pranav Constructions Limited
Redevelopment OF Rushabh Mahal Chsl
declared completion Jun 2025 · Pranav Constructions Limited
Redevelopment Of Sadguru Ashish Co-Op Housing Society Ltd
declared completion Oct 2024 · Bharati Constructions
Redevelopment Of Sanjog CHS Ltd
declared completion Nov 2022 · Heritage Lifestyles LLP
Redevelopment Of Saraswati Chsl
declared completion Dec 2025 · Rawoolnath Infrastructure Private Limite
Redevelopment OF SBI EMP Navjeevan Chsl
possession by Jul 2028 · Pranav Constructions Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026