MahaRERA Property Intelligence · Mumbai Suburban

REDEVELOPMENT OF SITA SADAN - RISHAB VILLA

P51800004365 · promoter Developers

Certificate SignedDue 30 Sep 2023

Delivery & Registration

MahaRERA registrationP51800004365
Registered on09 Aug 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
REDEVELOPMENT OF SITA SADAN - RISHAB VILLA1G+1930 Mar 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202330 Sep 2022DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 12 MPNTHS
30 Sep 202330 Sep 2023DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 30/09/2023

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400097. Per the filed land record, the plot is bounded to the north by JAY SARANG CHSL, to the south by MALAD SIVALAY CHSL, to the east by KALPVRUKH CHSL and to the west by HAJI BAPU ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~6 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ6 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad East

DEM Phoenix
possession by Jul 2026 · DEM Buildwell
Rajhans Solitaire
possession by Aug 2026 · Rajhans Residency
Amann Highland Park
possession by Oct 2026 · MS Relliance Construction CO
Gami And Jaydeep Ventura Commercial Hub
possession by Oct 2026 · M/S Real Infrastructure CO
Parmar Pearl - JAY Koteshwar Nagar CHS LTD
possession by Nov 2026 · Parmar Constructions Private Limited
Neelyog Virat -A Wing
possession by Dec 2026 · Neelyog Construction Pvt Ltd

Other RERA-registered projects in Mumbai Suburban

Redevelopment OF Sneh CHS
declared completion Dec 2022 · Japji Enterprises
Redevelopment OF Sparsh Chsl
declared completion Mar 2025 · Pranav Constructions Limited
Redevelopment Of Sri Guruvayurappan Balmukund Co-Operative Housing Society Ltd
declared completion Jun 2025 · Smera Homes LLP
Redevelopment OF State Bank OF India Employees Shree CO-OP Housing SOC LTD
declared completion Dec 2021 · Orra Realtors Private Limited
Redevelopment Of Sultanabad Darshan CHS Ltd
declared completion Dec 2021 · Aftab Constructions
Redevelopment OF THE Bandra GUL-E-Baug Chsl
possession by Jul 2028 · Pranav Constructions Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026