REDEVELOPMENT OF THE ROOPKALA CHS LTD

Mumbai City · ORRA REALTORS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010676

Delivery and registration

When is the project declared for completion?

REDEVELOPMENT OF THE ROOPKALA CHS LTD is registered with MahaRERA as P51800010676 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010676
Registered on31 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for REDEVELOPMENT OF THE ROOPKALA CHS LTD record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Orra Realtors is the promoter of record on 4 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

4projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for REDEVELOPMENT OF THE ROOPKALA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
THE ROOP KALA CHS LTD1G+14-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400054. Per the filed land record, the plot is bounded to the north by CTS NO 453, to the south by CTS NO 451, to the east by WEST AVENUE ROAD and to the west by CTS NO 444. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Chhatrapati Shivaji Int'l Airport3 km
Bandra Kurla Complex (BKC)4 km
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park9 km
Lower Parel / Worli business district9 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Orra Realtors Private Limited is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Orra Realtors Private Limited

Orra Realtors Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Santacruz West

Woodstock Gardens
possession by Oct 2026 · Woodstock Realties Private Limited
Artteza
possession by Nov 2026 · Sunvision Estates
M.K Heritage
Not filing quarterly progress reports · possession by Dec 2026 · Shaista Majid Khan
Cyrilyn
possession by Dec 2026 · Not Available
JAY Krupa Sadan BY Shree Hari Realty
possession by Dec 2026 · Shree Hari Realty
Orchid Vasundhara
possession by Dec 2026 · Orchid Builtcon Pvt. Ltd.

Major developers building in Santacruz West

Other RERA-registered projects in Mumbai Suburban

Redevelopment OF Tiara Chsl
declared completion Oct 2024 · Pranav Constructions Limited
Redevelopment OF Union Bank OF India Employees Ankur Chsl
possession by Feb 2027 · Pranav Constructions Limited
Redevelopment Of Vasishtha Krupa Co-Operative Housing Society Ltd
declared completion Aug 2025 · Kaustubh Construction Private Limited
Redevelopment Of Vijayshree Chsl
possession by Dec 2027 · Heritage Lifestyles & Developers Pvt
Redevelopment OF Vishva Anand CHS LTD
declared completion Dec 2019 · R R Constructions
Redevlopement Of SBI Madhur Milan Chsl
possession by Dec 2027 · Heritage Lifestyles And Developers Pvt.

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026