MahaRERA Property Intelligence · Mumbai Suburban

REDEVELOPMENT OF SPARSH CHSL

P51800031623 · MUMBAI · promoter Pranav Constructions Limited

Certificate SignedDue 31 Mar 2025

Delivery & Registration

MahaRERA registrationP51800031623
Registered on03 Nov 2021
Promoter-declared completion31 Mar 2025
Current statusCertificate Signed
Against todayabout 16 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Pranav Constructions Limited is the promoter of record on 60 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
REDEVELOPMENT OF SPARSH CHSL1G+1531 Mar 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at MUMBAI, 16 JANKALYAN NAGAR KHARODI MALAD WEST, Borivali, Mumbai Suburban, 400095. Per the filed land record, the plot is bounded to the north by CTS NO 9 11, to the south by CTS NO 26 27 AND 28, to the east by CTS NO 20 21 AND 22 and to the west by CTS NO 9 18. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Pranav Constructions Limited is the promoter on 45 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Pranav Constructions Limited project & its RERA track record →

Other flagged projects by Pranav Constructions Limited

Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban
Pranav Constructions Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Malad West

Anandam
possession by Aug 2026 · M/s Analiza Realty Pvt. Ltd.
95 West Composite
possession by Dec 2026 · Stans Buildtech Realty
BAY VUE
possession by Dec 2026 · H AND Y Realities Private Limited
Galaxy Heights Tower 1
possession by Dec 2026 · Maharashtra Police Cooperative Housing F
Lotus
possession by Dec 2026 · Rajeshwar Land Developers Private Limite
Royal Lagoon E Wing
possession by Dec 2026 · Rikki Ronie Developers

Other RERA-registered projects in Mumbai Suburban

Redevelopment Of Sri Guruvayurappan Balmukund Co-Operative Housing Society Ltd
declared completion Jun 2025 · Smera Homes LLP
Redevelopment OF State Bank OF India Employees Shree CO-OP Housing SOC LTD
declared completion Dec 2021 · Orra Realtors Private Limited
Redevelopment Of Sultanabad Darshan CHS Ltd
declared completion Dec 2021 · Aftab Constructions
Redevelopment OF THE Bandra GUL-E-Baug Chsl
possession by Jul 2028 · Pranav Constructions Limited
Redevelopment OF THE Roopkala CHS LTD
declared completion Dec 2018 · Orra Realtors Private Limited
Redevelopment OF THE State Bank OF India Siddheshwar CO OP Housing SOC LTD
declared completion Dec 2017 · Orra Realtors Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.