30 Jun 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000028771

Delivery and registration

When is the project declared for completion?

ROSE ENCLAVE is registered with MahaRERA as P99000028771 and the promoter has declared completion for 30 Jun 2025.

30 Jun 2025

declared completion

15months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000028771
Registered on30 Mar 2021
Promoter-declared completion30 Jun 2025
Current statusCertificate Signed
Against todayabout 15 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROSE ENCLAVE record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for ROSE ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
ROSE ENCLAVE1G+531 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NR SHANI MANDIR, CHANDANSAR ROAD, Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by PROPERTY OF BALKRISHNA L PATIL, to the south by BOUNDRY OF S NO 44 H NO 3, to the east by PROPERTY OF DADU L PATIL and to the west by BOUNDRY OF S NO 1. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Radheya Enterprises
possession by Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
possession by Dec 2026 · VED Ganga

Other RERA-registered projects in Palghar

Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
Royal Classic
declared completion Dec 2023 · Colour Developers
Royal Dreams Pride
possession by Dec 2027 · Albert Augstin Rodrigues
Royal Elegance
possession by Dec 2028 · Royal IB Infrastructure Private Limited
Royal Enclave
declared completion Sep 2020 · Mahalaxmi Enterprise
Royal Garden
possession by Jun 2027 · Imax Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026