Mumbai/Project record

MahaRERA · the public record

Royal Heritage

Shahapur · Build Green Infraprojects Private Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700048268

Delivery and registration

When is the project declared for completion?

Royal Heritage is registered with MahaRERA as P51700048268 and the promoter has declared completion for 30 Nov 2025.

30 Nov 2025

declared completion

10months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700048268
Registered on22 Dec 2022
Promoter-declared completion30 Nov 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Royal Heritage record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Build Green Infraprojects is the promoter of record on 75 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

75projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Royal Heritage in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+3.

BuildingWingsFloorsDeclared completion
Royal Heritage Wing-A1G+330 Nov 2025
Royal Heritage Wing-B1G+330 Nov 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Shahapur, Shere, Mumbai, Mumbai Suburban, 421601. Per the filed land record, the plot is bounded to the north by Plot No 67, to the south by 9 Meter Internal Road, to the east by Open Space for Garden and to the west by 12 Meter Internal Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Shahapur

Awasare Heights
possession by Sep 2026 · Rajkumar Tuljaram Aswani
Krishna Crown
possession by Oct 2026 · Shree Krishna Reality
Sava Arcade
possession by Oct 2026 · Sava Developers
Shantaram Park Residency
possession by Dec 2026 · Shubha Developers
Darshan Ganesh Apartment
possession by Dec 2026 · Tirupati Construction
Chintamani Meadows
possession by Dec 2026 · Jashnani Construction Private Limited

Major developers building in Shahapur

Other RERA-registered projects in Thane

Royal Heritage
possession by Dec 2028 · Mumbai Promoters Private Limited
Royal Manor
declared completion Jun 2024 · Abdul Gulampeer Shaikh
Royal Meadows
declared completion May 2026 · Siddh Enterprises
Royal Meadows C 1 , C 2
declared completion Dec 2025 · Siddhivinayak Developers
Royal Nest
declared completion Jun 2023 · Dhanashree Developers
Royal Orchid
declared completion Dec 2023 · S S Enterprises

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026