MahaRERA Property Intelligence · Mumbai Suburban

ROYALE HERRITAGE

P51800026314 · ANDHERI WEST · promoter Yogi Build Corporation

Certificate SignedDue 30 Sep 2024

Delivery & Registration

MahaRERA registrationP51800026314
Registered on07 Sep 2020
Promoter-declared completion30 Sep 2024
Current statusCertificate Signed
Against todayabout 22 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
ROYALE HERRITAGE1G+1031 Mar 2024

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000022064031/03/2022Chinar Realty Private Limited vs Yogi Build Corporationorder passed

Location, Land & Connectivity

Located at ANDHERI WEST, D.N NAGAR, Andheri, Mumbai Suburban, 400053. Per the filed land record, the plot is bounded to the north by EXISTING BUILDING ONGC SOCIETY, to the south by MAHALAXMI TOWER, to the east by EXISTING BUILDING ONGC SOCIETY and to the west by 9 METER BY LAYOUT ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Hubtown Premiere Residences - Bel Air
possession by Jul 2026 · Hubtown Limited
Morya Grand
possession by Jul 2026 · Nakta Investment Pvt. Ltd.
Umang Heights
possession by Aug 2026 · L K Infracon LLP
Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Royale Residences B And C Wing
declared completion Jun 2022 · M/s Rani Creators , Consultant And Servi
Royale Rose
possession by Dec 2028 · Project One
Royce Residences
possession by Jun 2030 · Maxrich Infra Private Limited
Ruby CHS
declared completion Mar 2019 · Hasmukh R Hirani
Ruchi Chsl
possession by Mar 2030 · Protsahan Developers LLP
Rudani Pride Kailash Park F Plot A Wing
possession by Dec 2027 · Umiya Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026