Mumbai/Project record

MahaRERA · the public record

Ruparel Zion

Sion · ARISE DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900014944

Delivery and registration

When is the project declared for completion?

Ruparel Zion is registered with MahaRERA as P51900014944 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900014944
Registered on15 Jan 2018
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ruparel Zion record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Arise Developers is the promoter of record on 5 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ruparel Zion in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21.

BuildingWingsFloorsDeclared completion
Circle Pride CHS1G+2131 Dec 2021

Legal and disputes

What disputes are disclosed?

3 complaints are on the MahaRERA record for Ruparel Zion, with orders passed in 3 of them.

3complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039700426/08/2023Sharad Laxmichand Dhulla vs Arise Developersorder passed
CC00600000042892821/01/2024Amit Krushna Nipane vs Amit Ruparelorder passed
CC1250020321/01/2025Dhaval Pravin Gala vs ARISE DEVELOPERSorder passed

Location, Land & Connectivity

Located at Sion, Road No 28 A, Mumbai City, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by CS no 394-5 and 395-6, to the south by road No 28 A, to the east by road No 28 A and to the west by road No 28 B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Lower Parel / Worli business district4 km
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park11 km
Andheri MIDC / SEEPZ11 km
Nariman Point / Fort12 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Arise Developers is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Arise Developers

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD
Panchratna-NX
possession by Dec 2026 · Sudhir Kishor Desai

Other RERA-registered projects in Mumbai City

Rupji Arena
declared completion Dec 2018 · Rupji Constructions
Rupji Swapnapurti
declared completion Jul 2022 · Rupji Constructions
Rusi Mehta Towers
declared completion Dec 2021 · Anahita Rusi Mehta
Rustomjee 180 Bayview Matunga W - Wing A
possession by Dec 2029 · RAJ Doshi Exports Private Limited
Rustomjee 180 Bayview Matunga W - Wing B
possession by Jun 2029 · RAJ Doshi Exports Private Limited
Rustomjee Crown -Phase II
declared completion Jun 2026 · Realgem Buildtech Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026