MahaRERA Property Intelligence · Thane

SAHAYOG NILAYAM

P51700008289 · Manda · promoter Sahayog Construction

Certificate SignedDue 30 Oct 2023

Delivery & Registration

MahaRERA registrationP51700008289
Registered on18 Aug 2017
Promoter-declared completion30 Oct 2023
Current statusCertificate Signed
Against todayabout 33 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sahayog Construction is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SAHAYOG NILAYAM - A WING1G+831 Oct 2022
SAHAYOG NILAYAM B-WING1G+731 Oct 2022
SAHAYOG NILAYAM C- WING1G+731 Oct 2022

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000042872607/01/2024SAHAYOG NILAYAM vs KALPAK RATILAL SHAHorder passed

Location, Land & Connectivity

Located at Manda, Sangoda Road, Kalyan, Thane, 421605. Per the filed land record, the plot is bounded to the north by CTS NO 955, to the south by SANGODA ROAD, to the east by CTS NO 946 PART 952 and to the west by CTS NO 958 959 960 961. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~37 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park37 km
Andheri MIDC / SEEPZ39 km
Chhatrapati Shivaji Int'l Airport42 km
Bandra Kurla Complex (BKC)43 km
Lower Parel / Worli business district51 km
Nariman Point / Fort57 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Titwala

Marathe Tower
possession by Jul 2026 · Saiji Developers
Marathe Elenza
possession by Jul 2026 · Saiji Developers
Ganpati Heights
possession by Sep 2026 · Manoj Prabhakar Patil
Indrayani
possession by Oct 2026 · Naresh Yashwant Patil
Mantra
possession by Nov 2026 · Vaidikh Nirmaan LLP
Rusttagi Aarambha 2.0
possession by Nov 2026 · Rustagi Estates Private Limited

Other RERA-registered projects in Thane

Sahayog Niwas
declared completion Jan 2020 · Shree Developers
Sahyadri Elite
possession by Mar 2028 · Sikeria Shelter Private Limited
Sahyadri Lifespaces
possession by Jun 2030 · Sahyadri Lifespaces
Sahyadri Residency Phase I
declared completion Dec 2023 · M/S Nirman Developers
Sahyadri Villas
declared completion Nov 2019 · Ashoka Dreams Developers
Sahyog IBM
declared completion Dec 2024 · S S Construction

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026