SAI DARSHAN

ANDHERI · SHAH PATEL & CO

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

9units filed as unsoldInventory · 16 September 2026
31 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
34registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800013711

Delivery and registration

When is the project declared for completion?

SAI DARSHAN is registered with MahaRERA as P51800013711 and the promoter has declared completion for 31 Dec 2024.

31 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800013711
Registered on23 Oct 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI DARSHAN record 29 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 29 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shah Patel is the promoter of record on 175 projects registered with MahaRERA, 30 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

175projects

registered with MahaRERA

30flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SAI DARSHAN, 10 of 21 homes filed with MahaRERA are recorded as sold or booked (9 with registered agreements and 1 booked), about 48%, and 11 remain available.

48%sold

10 of 21 homes

₹11.89 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹9.83 Cr (about 83%) is recorded as collected and ₹2.07 Cr as receivable. The project registers 34 homes in total, while this sold/unsold inventory filing covers 21 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 10 registered agreements, the effective carpet rate is ₹20,492/sqft, with eight in ten falling between ₹20,147 and ₹22,362 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1103584 sqft (54.3 sqm)₹1.21 Cr
Floor 1104664 sqft (61.72 sqm)₹1.38 Cr
Floor 2203584 sqft (54.3 sqm)₹1.21 Cr
Floor 2204664 sqft (61.72 sqm)₹1.38 Cr
Floor 3304664 sqft (61.72 sqm)₹1.38 Cr
Floor 5503576 sqft (53.49 sqm)₹1.20 Cr
Floor 7704664 sqft (61.72 sqm)₹1.38 Cr
Floor 8801423 sqft (39.29 sqm)₹87.86 Lakh
Floor 8804664 sqft (61.72 sqm)₹1.38 Cr
Floor 9903576 sqft (53.49 sqm)₹1.20 Cr
Floor 9904664 sqft (61.72 sqm)₹1.38 Cr

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 12 homes carry one, and 9 of the 21 are recorded unsold. Since we started watching this ledger, 2 homes have moved out of the unsold list, most recently on 08 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
103584 sqftRs 1.1850 cr typical, over Rs 1.1600 cr to Rs 1.2950 cr6 filed on this stack, floors 2–8

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SAI DARSHAN, every one of the 9 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 8 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 34 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SAI DARSAN1G+1034-

Unit mix on the filing: 34 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered29 Dec 2022The construction of the project "SAI DARSHAN" got delayed on account of pandemic situation across country due to COVID 19.The construction work on site affected due to non availab
29 Dec 202231 Dec 2023We, hereby apply for extension u/s 7(3) of the registered project beari ng vide no P51800013711
31 Dec 202331 Dec 2024Presently the project in completed in all respect, however we are expecting final Occupancy Certificate within six months’ time. Further we would like reiterate that the constructi

Location, Land & Connectivity

Located at ANDHERI, OFF VEERA DESAI ROAD, Borivali, Mumbai Suburban, 400058. Per the filed land record, the plot is bounded to the north by CTS NO 66, to the south by CTS NO 73, to the east by CTS NO 68 AND 72 and to the west by MATRAPADA ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)8 km
Powai / Hiranandani business park8 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
Registration suspended · possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya
La Alteza
possession by Dec 2026 · Emerald Developers

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Sai Divine
possession by Dec 2027 · Shreeji Developers
Sai Divine B And C
possession by Dec 2027 · Shreeji Developers
SAI Elegance
possession by Sep 2026 · Nirav Thaker Buildcon LLP
Sai Jyoti
possession by Dec 2026 · Shambhavi Enterprises
Sai Kripa Ressidency
possession by Jun 2027 · OM SAI SSS Developers Thane
SAI Krupa CHS LTD
declared completion Jun 2023 · S D Bhalerao Constructions PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026