SAI EKVIRA SADAN

Mumbai City · K Merchant Construction Ltd

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012655

Delivery and registration

When is the project declared for completion?

SAI EKVIRA SADAN is registered with MahaRERA as P51900012655 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012655
Registered on07 Sep 2017
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI EKVIRA SADAN record 18 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 18 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Merchant Construction Ltd is the promoter of record on 15 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

15projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI EKVIRA SADAN in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19.

BuildingWingsFloorsDeclared completion
WING A AND B1G+19-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SAI EKVIRA SADAN, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000010020918/07/2019Rajavi Rajendra Niak and other twelve vs m/s k merchant construction Ltdorder passed
CC00600000039580619/05/2023PHOOLCHAND JAIN vs M/s K Merchant Construction pvt Ltsorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Girgaon300 PW 20172017Pending
V Desai Court23865 AND 6402016Pending
Shinde Wadi330 TO 3372015Pending

Location, Land & Connectivity

Located at Ward ABCD, Mumbai City, 400004. Per the filed land record, the plot is bounded to the north by C S NO 287, to the south by MUGHBAT CROSS LANE, to the east by MUGHBAT LANE and to the west by C S NO 289. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort4 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)13 km
Chhatrapati Shivaji Int'l Airport15 km
Andheri MIDC / SEEPZ20 km
Powai / Hiranandani business park20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

K Merchant Construction Ltd is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Girgaum

Aaditya Residences
possession by Dec 2026 · M/s. A.k. Developers
Shreepati Bayview
Deregistered by MahaRERA · possession by Dec 2026 · Shreepati Build Infra Investment Limited
NEO Amity
possession by Dec 2026 · Naresh Kesarimal Mehta
Onyx
possession by Dec 2026 · Naminath Erector And Developers LLP
Promesa Castor
possession by Dec 2026 · Darshan Group
Raajdeep Arcade
possession by Dec 2026 · Raajdeep Builders AND Developers

Other RERA-registered projects in Mumbai City

SAI Heights
declared completion Dec 2021 · SAI Construction
SAI Nandadeep
declared completion Mar 2021 · Baburao Deoji Patil
Saif Towers
declared completion Dec 2025 · Mustanshir Saifuddin Merchant
Saivishwa
declared completion Jun 2025 · Snehalkumar Chandrakant Nadkarni
Salsette27 Centre
possession by Mar 2028 · Goodtime Real Estate Development Private
Samarth Raghukul
declared completion Dec 2017 · M/S Virtue Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026