28 Jun 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

28 Jun 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020382

Delivery and registration

When is the project declared for completion?

SAI FLORA is registered with MahaRERA as P51700020382 and the promoter has declared completion for 28 Jun 2028.

28 Jun 2028

declared completion

21months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020382
Registered on09 Apr 2019
Promoter-declared completion28 Jun 2028
Current statusCertificate Signed
Against today21 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI FLORA record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI FLORA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
DAFFODIL1G+16-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered28 Jun 2028I, Mr. Vikas Maruti Kokane, Authorized Partner of Sai Raj Developers, state that we have registered a project named SAI FLORA, situated at Plot Nos. 46/13 A, 46/13 B, 46/13 C, and

Location, Land & Connectivity

Located at AMBIVALI EAST, YADAV NAGAR ROAD, Kalyan, Thane, 421102. Per the filed land record, the plot is bounded to the north by 19153496 -73102573, to the south by 79153079-73102459, to the east by 19153462 -73102852 and to the west by 19153167 -73102271. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district30 km
Nariman Point / Fort38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI RAJ Developers is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Ambivali West

Godrej Riviera Phase 1
possession by Dec 2026 · Godrej Properties Limited
Gaikwad Residency
possession by Dec 2026 · Niwara Group
Gangubai Height
possession by Dec 2026 · Vinayak Construction
Ashapura Galaxy
possession by Mar 2027 · Ashapura Estates
Lotus Residency
possession by Mar 2027 · Kulvinder Infrastructure Private Limited
Neptune Triveni Sangam
Developer in insolvency (NCLT) · possession by Jul 2027 · Neptune Developers Limited

Major developers building in Ambivali West

Other RERA-registered projects in Thane

Sai Flora
possession by Dec 2026 · M/S Mitra Reality
SAI Flora-Type B
possession by Jun 2028 · Sairaj Developers
SAI Galaxy
declared completion Mar 2023 · Sanchi Construction
SAI Galaxy
possession by Mar 2027 · M/s. Western Arch Company
Sai Galaxy A- Wing And C- Wing
possession by Dec 2026 · Jash Developers
Sai Galaxy B-Wing
declared completion Jun 2026 · Jash Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026