Mumbai/Project record

MahaRERA · the public record

SAI PARADISE

Mumbai Suburban · SAI UNIVERSAL REALTORS & DEVELOPERS LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008929

Delivery and registration

When is the project declared for completion?

SAI PARADISE is registered with MahaRERA as P51800008929 and the promoter has declared completion for 31 Mar 2026.

31 Mar 2026

declared completion

6months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008929
Registered on19 Aug 2017
Promoter-declared completion31 Mar 2026
Current statusCertificate Signed
Against todayabout 6 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI PARADISE record 35 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sai Universal Realtors is the promoter of record on 85 projects registered with MahaRERA, 9 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

85projects

registered with MahaRERA

9flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI PARADISE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Lotus A1G+530 Apr 2020
DAFFODIL B11G+530 Apr 2020
MARIGOLD B11G+530 Apr 2020
TULIP C1G+530 Apr 2020
ORCHID C11G+430 Apr 2020
ROSE B21G+830 Apr 2020
ROSE B21G+830 Apr 2020

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SAI PARADISE , with orders passed in 0 of them.

2complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260177727/03/2026Deepak R Varma vs SAI UNIVERSAL REALTORS & DEVELOPERS LLPpending / no order on file
CC1260178027/03/2026Deepak R Varma vs SAI UNIVERSAL REALTORS & DEVELOPERS LLPpending / no order on file

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020I MR. DEEPAK BANSAL, PARTNER OF M/S SAI UNIVERSAL REALTORS & DEVELOPERS LLP. WANTS TO STATE THAT OUR PROJECT SAI PARADISE LOCATED IN CTS NO 741 H NO. 2 AT VILLAGE SHIRGAON PALGHAR.
30 Apr 202031 Dec 2021Respected Sir, We have completed project and the project is due for receipt of Occupancy Certificate. However, Due to reduction of working hours of Staff of the Townplanning and o
31 Dec 202131 Mar 2026Respected Sir, We have completed project and the project is due for receipt of Occupancy Certificate. However, Due to reduction of working hours of Staff of the Town planning and

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400066. Per the filed land record, the plot is bounded to the north by GOVERNMENT LAND , to the south by SHIRGAON SATPATI SERVICE ROAD , to the east by CTS NO 741-6 TUKARAM NARAYAN MALI- POPATLAL SHAH and to the west by INTERNAL ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~11 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park13 km
Chhatrapati Shivaji Int'l Airport16 km
Bandra Kurla Complex (BKC)18 km
Lower Parel / Worli business district26 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

SAI Universal Realtors & Developers LLP is the promoter on 3 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by SAI Universal Realtors & Developers LLP

SAI Universal Realtors & Developers LLP
Not filing quarterly progress reportsMumbai Suburban
SAI Universal Realtors & Developers LLP
Past its declared completion datePalghar

Other RERA-registered projects in Borivali East

Proposed Redevelopment OF Prakashkunj Chsl
possession by Sep 2026 · Yash Realtors & Developers
Chandratej CHS LTD
possession by Oct 2026 · Elesh Ravjibhai Rathod
Eknath Gruh
possession by Oct 2026 · Vastav Developers PVT LTD
NEW Avanti Chsl
possession by Oct 2026 · Balaji Enterprises
Empire Vrindavan
possession by Nov 2026 · Empire Realty
66 Avenue
possession by Dec 2026 · Parsh Realtors

Major developers building in Borivali East

Other RERA-registered projects in Mumbai Suburban

Sai Saburi
possession by Dec 2027 · Pardis LA LLP
SAI Sastha Samrat
declared completion Dec 2025 · MS SAI Sastha Enterprises
SAI Shankar
possession by Dec 2028 · Shree Sai Realtors
Sai Shrushti
possession by Dec 2027 · Shree Sai Realtors
Sai Shrusti CHS
possession by Dec 2027 · Shree Swami Samarth Buildcon
Sai Siddhi Chsl
possession by Dec 2028 · SAI Siddhi Builders AND Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026