Mumbai/Project record

MahaRERA · the public record

SAI SHANTI PARK - AARADHYA C-D

Thane · MARVEL LIFESPACES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000004026

Delivery and registration

When is the project declared for completion?

SAI SHANTI PARK - AARADHYA C-D is registered with MahaRERA as P52000004026 and the promoter has declared completion for 30 Dec 2020.

30 Dec 2020

declared completion

69months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000004026
Registered on07 Aug 2017
Promoter-declared completion30 Dec 2020
Current statusCertificate Signed
Against todayabout 69 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI SHANTI PARK - AARADHYA C-D record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI SHANTI PARK - AARADHYA C-D in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
AARADHYA C-D1G+5-

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for SAI SHANTI PARK - AARADHYA C-D, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000017166328/11/2019Ashok Bharadwaj vs Dinesh Bhanushaliorder passed
CC00600000019373018/08/2020Aradhya Flat Owners Welfare Association vs Marvel Life Spacesorder passed

Location, Land & Connectivity

Located at Thane, Thane, 410208. Per the filed land record, the plot is bounded to the north by BUILDING NO 4 ANANYA, to the south by 9 MTR WIDE ROAD, to the east by SURVEY NO 2 H NO- 64 and to the west by BUILDING NO 3 - ANAND AND BLDG NO 5- AARADYA A-B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~20 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park20 km
Bandra Kurla Complex (BKC)24 km
Andheri MIDC / SEEPZ24 km
Chhatrapati Shivaji Int'l Airport24 km
Lower Parel / Worli business district30 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Marvel Lifespaces is the promoter on 4 MahaRERA-registered projects, of which 4 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Marvel Lifespaces

Marvel Lifespaces
Past its declared completion dateRaigarh
Marvel Lifespaces
Past its declared completion dateRaigarh
Marvel Lifespaces
Past its declared completion dateRaigarh

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
Om Unnati
possession by Nov 2026 · Om Group
Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited

Other RERA-registered projects in Raigarh

SAI Shanti Park - Anand
declared completion Dec 2022 · Marvellifespaces
SAI Shanti Park - Ananya
declared completion Jun 2022 · Marvel Lifespaces
SAI Shanti Park Asha AND Akanksha
declared completion Mar 2022 · Marvel Lifespaces
Sai Shell
possession by Mar 2029 · Surekha Tukaram Dudhe
SAI Shivam Hill View
declared completion Dec 2023 · SAI Shivam Enterprises
SAI Shivam Residency
declared completion Oct 2022 · SAI Shivam Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026