SAKSHI APARTMENT

KELVE ROAD EAST · OM BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

32units filed as unsoldInventory · 18 September 2026
31 Jul 2031declared completionMahaRERA registration · read 10 Sep 2026
32registered unitsMahaRERA registration · read 10 Sep 2026

The record · free to read

Registration read 10 Sep 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2031

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 10 Sep 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PM1240002601370

Delivery and registration

When is the project declared for completion?

SAKSHI APARTMENT is registered with MahaRERA as PM1240002601370 and the promoter has declared completion for 31 Jul 2031.

31 Jul 2031

declared completion

58months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 10 Sep 2026

MahaRERA registrationPM1240002601370
Registered on31 Jul 2026
Promoter-declared completion31 Jul 2031
Current statusCertificate Signed
Against today58 months to the declared date

Sales

How much has actually been sold?

In SAKSHI APARTMENT, 0 of 32 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 32 remain available.

0%sold

0 of 32 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 10 Sep 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101273 sqft (25.38 sqm)₹11.68 Lakh
Floor 1102292 sqft (27.14 sqm)₹12.63 Lakh
Floor 1103294 sqft (27.32 sqm)₹12.52 Lakh
Floor 1104252 sqft (23.38 sqm)₹10.94 Lakh
Floor 2201273 sqft (25.38 sqm)₹11.68 Lakh
Floor 2202292 sqft (27.14 sqm)₹12.63 Lakh
Floor 2203294 sqft (27.32 sqm)₹12.52 Lakh
Floor 2204252 sqft (23.38 sqm)₹10.94 Lakh
Floor 3301273 sqft (25.38 sqm)₹11.68 Lakh
Floor 3302292 sqft (27.14 sqm)₹12.63 Lakh
Floor 3303294 sqft (27.32 sqm)₹12.52 Lakh
Floor 3304252 sqft (23.38 sqm)₹10.94 Lakh
Floor 4401273 sqft (25.38 sqm)₹11.68 Lakh
Floor 4402292 sqft (27.14 sqm)₹12.63 Lakh
Floor 4403294 sqft (27.32 sqm)₹12.52 Lakh
Floor 4404252 sqft (23.38 sqm)₹10.94 Lakh
Floor 5501273 sqft (25.38 sqm)₹11.68 Lakh
Floor 5502292 sqft (27.14 sqm)₹12.63 Lakh
Floor 5503294 sqft (27.32 sqm)₹12.52 Lakh
Floor 5504252 sqft (23.38 sqm)₹10.94 Lakh
Floor 6601273 sqft (25.38 sqm)₹11.68 Lakh
Floor 6602292 sqft (27.14 sqm)₹12.63 Lakh
Floor 6603294 sqft (27.32 sqm)₹12.52 Lakh
Ground/Floor 0SHOP 0188 sqft (8.15 sqm)₹4.16 Lakh
Ground/Floor 0SHOP 0271 sqft (6.57 sqm)₹3.35 Lakh
Ground/Floor 0SHOP 03142 sqft (13.21 sqm)₹6.74 Lakh
Ground/Floor 0SHOP 04142 sqft (13.21 sqm)₹6.74 Lakh
Ground/Floor 0SHOP 05115 sqft (10.67 sqm)₹5.44 Lakh
Ground/Floor 0SHOP 06117 sqft (10.85 sqm)₹5.53 Lakh
Ground/Floor 0SHOP 07124 sqft (11.53 sqm)₹5.88 Lakh
Ground/Floor 0SHOP 0878 sqft (7.25 sqm)₹3.70 Lakh
Ground/Floor 0SHOP 0970 sqft (6.46 sqm)₹3.29 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAKSHI APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 18 September 2026

What the filings record, home by home

Read from MahaRERA on 18 September 2026

No home in SAKSHI APARTMENT carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 32 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 4,323 a sq ft typical, over Rs 4,258 to Rs 4,738.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 32 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 32 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6 and 32 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING 1 A1G+632-

Unit mix on the filing: 23 residential and 9 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2031NA

Location, Land & Connectivity

Located at KELVE ROAD EAST, GUT NO - 719/1, Palghar, Palghar, 401401. Per the filed land record, the plot is bounded to the north by GUT NO 664, to the south by 7.5M WIDE PROPOSED ROAD, to the east by BUILDING 1B and to the west by 9.00 MTR WIDE EXISTING ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~56 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ56 km
Powai / Hiranandani business park58 km
Chhatrapati Shivaji Int'l Airport60 km
Bandra Kurla Complex (BKC)63 km
Lower Parel / Worli business district70 km
Nariman Point / Fort78 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Not Available is the promoter on 6 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Not Available

Not Available
FlaggedMumbai Suburban

Other RERA-registered projects in Kelve Road

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
possession by Dec 2026 · Sai Builders And Developers
Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
Savera Complex
Not filing quarterly progress reports · possession by Dec 2026 · Savera Builders & Developers
THE Hill Touch
possession by Dec 2026 · Aristone Infra
SK Swarnik Homes
possession by Feb 2027 · SK Swarnik Homes

Other RERA-registered projects in Palghar

Samaira Opulence
possession by Dec 2027 · Samaira Buildcon
Samaira Residency
possession by Dec 2026 · AV Crystal Space
Samarth Enclave
possession by Oct 2028 · Shashikant Tukaram Patil
Samarth Sai Residency
declared completion Mar 2026 · Vijay Sitaram Pimple
Samata CO-Operative Housing Society LTD
possession by Dec 2028 · Shree Ganesh Builders & Developers
Samriddhi Heights
possession by Dec 2028 · Samriddhi Elite LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 19 Aug 2026