Mumbai/Project record

MahaRERA · the public record

SALE BLDG B1 WING A B

ANDHERI EAST · Accord Land Developers Pvt Ltd

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800016975

Delivery and registration

When is the project declared for completion?

SALE BLDG B1 WING A B is registered with MahaRERA as P51800016975 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800016975
Registered on26 Jun 2018
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SALE BLDG B1 WING A B record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Accord Land Developers is the promoter of record on 10 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SALE BLDG B1 WING A B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
BINDRA ONE WING A B1G+1431 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at ANDHERI EAST, MAHAKALI CAVES ROAD, Andheri, Mumbai Suburban, 400093. Per the filed land record, the plot is bounded to the north by SATYA SAI BABA MANDIR, to the south by CTS NO 1 VYRAVALI, to the east by CTS NO 1 VYRAVALI and to the west by MAHAKALI ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Accord Land Developers Pvt Ltd is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Accord Land Developers Pvt Ltd

Accord Land Developers Pvt Ltd
FlaggedMumbai Suburban
Accord Land Developers Pvt Ltd
FlaggedMumbai Suburban
Accord Land Developers Pvt Ltd
FlaggedMumbai Suburban

Other RERA-registered projects in Andheri East

Inspire Residency
possession by Dec 2026 · Sardar Realty
Mahakali Hills
possession by Dec 2026 · Mohid Construction Co
Royal Fantasy Phase II
possession by Dec 2026 · Royal Fantasy Constructions Private Limi
Samarth Enclave F AND G Wing Andheri Chhaya CHS
possession by Dec 2026 · Samarth Erectors AND Developers
Samarth Enclave H Wing Andheri Chhaya CHS
possession by Dec 2026 · Samarth Erectors AND Developers
Zennith
possession by Dec 2026 · Apexbliss Infraventures Private Limited

Major developers building in Andheri East

Other RERA-registered projects in Mumbai Suburban

Sale Bldg NO. 6 Wing Known AS Northern Supremus & Northern Hills Building NO. 1 & 2
possession by Dec 2026 · N.rose Developers PVT LTD
Sale Building 1 - Chamunda Crown AND Sale Building 3 - Chamunda Classic
possession by Dec 2026 · Chamunda Builders & Developers
Sale Building No. 14 - Phase 1
declared completion Dec 2024 · Mangal Moorti Developers Private Limited
Samaj Kalyan CHS Ltd
declared completion Oct 2020 · Niraj Mansukhlal VED
Samarpan
declared completion Jun 2026 · HS Construction
Samarpan Sankalp
possession by Dec 2026 · Samarpan Homes & Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026