30 Oct 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800018812

Delivery and registration

When is the project declared for completion?

SAMARTHA GAURAV is registered with MahaRERA as P51800018812 and the promoter has declared completion for 30 Oct 2024.

30 Oct 2024

declared completion

23months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800018812
Registered on05 Dec 2018
Promoter-declared completion30 Oct 2024
Current statusCertificate Signed
Against todayabout 23 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMARTHA GAURAV record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Samartha Development Corporation is the promoter of record on 25 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

25projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMARTHA GAURAV in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
SAMARTHA GAURAV A WING1G+22-
SAMARTHA GAURAV B WING1G+15-
SAMARTHA GURAV C WING1G+13-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SAMARTHA GAURAV, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019789606/08/2021KALPVRUKSH DEVELOPERS vs SAMARTHA DEVELOPMENT CORPORATIONorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay High Court8022013Framing Issues
Bombay High Court462014Framing Issues

Location, Land & Connectivity

Located at OSHIWARA , 120 FT WIDE DP ROAD, Mumbai City, Mumbai City, 400053. Per the filed land record, the plot is bounded to the north by 120 FT WIDE DP ROAD, to the south by RG 5, to the east by NALLA and to the west by RG 4 PLOT NO 117. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Chhatrapati Shivaji Int'l Airport8 km
Powai / Hiranandani business park9 km
Bandra Kurla Complex (BKC)10 km
Lower Parel / Worli business district17 km
Nariman Point / Fort25 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Andheri West

Royale
possession by Sep 2026 · Khoker Synergy Developers
Transcon Triumph Tower 3
possession by Sep 2026 · Transcon Triumph Phase 2 Private Limited
ARC ONE
possession by Dec 2026 · Chandra Gupta Estates Private Limited
MDM Maestro
possession by Dec 2026 · MDM Realty LLP
Platinum Grandeur
possession by Dec 2026 · Platinum Strategic Developers LLP
Vengurlekars Chaitra
possession by Dec 2026 · Vengurlekars Shreesai Builders And Devel

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Sambhav Darshan Purshottam Park CO-Operative Housing Society LTD
possession by Dec 2027 · Samarpan Homes & Developers
Samosaran Apartments
declared completion Dec 2022 · Mahavir Construction Company
Sampoorna
possession by Apr 2027 · Narayanprasad Mahadevan
Samriddhi Garden Wing C Gulmohar Wing D Deodhar
declared completion Oct 2025 · Sivana Realty Private Limited
Samruddhi
possession by Dec 2029 · Shree SAI Bhoomi Realtors
Samruddhi Heights
declared completion Dec 2023 · Not Available

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026