MahaRERA Property Intelligence · Mumbai Suburban

SAMRUDDHI HEIGHTS

P51800015900 · Pahadi Goregaon (West) · promoter Sarathi Construction

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51800015900
Registered on04 Apr 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sarathi Construction is the promoter of record on 2 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~73.8% of the estimated project cost incurred as of the last certificate (₹19.66 Cr spent against a ₹26.65 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows. The declared completion date has already passed while the cost-incurred filing sits at ~73.8% — a wide gap between the promise and the money actually spent on site.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 33 homes filed with MahaRERA, 25 are sold/booked and 8 remain available (~76% sold) — selling steadily. Buyers have committed ₹29.69 Cr in agreement value so far. Of that, ₹21.48 Cr (~72%) is already collected, ₹8.21 Cr receivable — a read on how far along these sales really are. Note: the project registers 69 homes in total, but this sold/unsold inventory filing covers only 33 of them — the other 36 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 25 registered agreements, the effective carpet rate is ₹18,560/sqft (typical range ₹16,874–₹20,999) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 121203645 sqft (59.92 sqm)₹1.06 Cr
Floor 141404645 sqft (59.92 sqm)₹1.06 Cr
Floor 161601612 sqft (56.86 sqm)₹1.00 Cr
Floor 181802612 sqft (56.86 sqm)₹1.00 Cr
Floor 181803645 sqft (59.92 sqm)₹1.06 Cr
Floor 181804645 sqft (59.92 sqm)₹1.06 Cr
Floor 6604481 sqft (44.69 sqm)₹78.88 Lakh
Floor 7702586 sqft (54.44 sqm)₹96.10 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+19 and 69 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SAMRUDDHI HEIGHTS1G+196931 Dec 2026

Unit mix on the filing: 69 residential.

Complaints & Orders

10 complaints are on the MahaRERA record for this project, with orders passed in 7. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000037512706/04/2023Gautam Pradeep Ghadge vs M/S SARATHI CONSTRUCTIONorder passed
CC00600000037515006/04/2023SIDDHARTHA PRADEEP GHADGE vs M/S SARATHI CONSTRUCTIONorder passed
CC00600000042913116/02/2024Satish Mahabaleshwar Ambe vs Mrs Savita Ghanshyam Gajareorder passed
CC00600000042934520/02/2024Dilip Ratilal Chudasama vs SAVITA GHANSHYAM GAJAREorder passed
CC1240040212/10/2024Sarvesh Sampati Yadav vs SAVITA GHANSHYAM GAJAREorder passed
CC1250329015/09/2025SAVITA GHANSHYAM GAJARE vs Bhavya Pankaj shahorder passed
CC1250329115/09/2025SAVITA GHANSHYAM GAJARE vs Disha Pankaj Shahorder passed
CC1250379830/10/2025SIDDHARTHA PRADEEP GHADGE vs SAVITA GHANSHYAM GAJAREpending / no order on file
CC1250459423/12/2025Shailesh Malekar vs SAVITA GHANSHYAM GAJAREpending / no order on file
CC1260118304/03/2026Gautam Pradeep Ghadge vs SAVITA GHANSHYAM GAJAREpending / no order on file

Location, Land & Connectivity

Located at Pahadi Goregaon (West), Unnat Nagar 2, Borivali, Mumbai Suburban, 400062. Per the filed land record, the plot is bounded to the north by CTS 306B, to the south by CTS 305, to the east by DP ROAD 9m wide and to the west by CTS 305. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district19 km
Nariman Point / Fort27 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other flagged projects by Not Available

Not Available
FlaggedMumbai Suburban
Not Available
FlaggedMumbai Suburban

Other RERA-registered projects in Goregaon West

Modirealty Vatvriksh
possession by Sep 2026 · Modirealty Developers PVT LTD
Devtaa Pratham
possession by Dec 2026 · Vipul Mitra CO-Operative Housing Society
Manju Villa
possession by Dec 2026 · Meghna Developers AOP
Nirlon Employees CHS LTD Building NO. 10
possession by Dec 2026 · Shivam Parivar Developers Private Limite
Happy Home Enclave
possession by Dec 2026 · JD & FC Ventures LLP
Laxmi Leela Arhum
possession by Dec 2026 · Laxmi Leela Constructions LLP

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Samta
declared completion Aug 2022 · Green Tree Lifescapes LLP
Samyakth Bliss Building 2
declared completion Dec 2017 · Samyakth Realties
Samyakth Bliss Tower B
possession by Dec 2026 · Samyakth Realties
Sana Arcade
declared completion Dec 2019 · Kadri Construction CO.
Sana Crystal
possession by May 2027 · M/S Sana Enterprises
Sana Enclave
possession by Sep 2027 · Sana Enterpises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026