Mumbai/Project record

MahaRERA · the public record

SATYAM

JOGESHWARI EAST · PODDAR INFRACON PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

5units filed as unsoldInventory · 18 September 2026
31 Aug 2026declared completionMahaRERA registration · read 12 Jul 2026
58registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800045715

Delivery and registration

When is the project declared for completion?

SATYAM is registered with MahaRERA as P51800045715 and the promoter has declared completion for 31 Aug 2026.

31 Aug 2026

declared completion

1months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800045715
Registered on06 Jun 2022
Promoter-declared completion31 Aug 2026
Current statusCertificate Signed
Against todayabout 1 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SATYAM record 16 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 16 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In SATYAM, ₹47.94 Cr of a declared ₹49.48 Cr estimated project cost is reported as incurred, about 96.9%, as at the last certified filing with MahaRERA.

96.9%

₹47.94 Cr

of ₹49.48 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In SATYAM, 50 of 58 homes filed with MahaRERA are recorded as sold or booked, about 86%, and 8 remain available.

86%sold

50 of 58 homes

₹40.38 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹33.24 Cr (about 82%) is recorded as collected and ₹7.14 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 50 registered agreements, the effective carpet rate is ₹12,564/sqft, with eight in ten falling between ₹1,059 and ₹24,451 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 121204654 sqft (60.77 sqm)₹69.00 Lakh
Floor 121205654 sqft (60.77 sqm)₹68.89 Lakh
Floor 131301774 sqft (71.91 sqm)₹81.91 Lakh
Floor 131302741 sqft (68.84 sqm)₹78.42 Lakh
Floor 131303449 sqft (41.71 sqm)₹47.51 Lakh
Floor 131304670 sqft (62.23 sqm)₹70.89 Lakh
Floor 131305651 sqft (60.48 sqm)₹68.89 Lakh
Floor 151505651 sqft (60.48 sqm)₹68.89 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 53 homes carry one, and 5 of the 58 are recorded unsold. Since we started watching this ledger, 3 homes have moved out of the unsold list, most recently on 09 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
1302741 sqftRs 1.5000 cr typical, over Rs 15.43 lakh to Rs 1.7000 cr9 filed on this stack, floors 2–12

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In SATYAM, every one of the 5 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 4 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13 and 58 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SATYAM1G+1358-

Unit mix on the filing: 58 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SATYAM, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000039795626/10/2023Usha Sachdeva vs Satyam CHS Ltdpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay City Civil Court2013562014Ongoing
Bombay City Civil Court02013562014Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Aug 2026We were awaiting the Further CC in the project which has been granted upto 17th floor from initial 7 floors. Accordingly, plan has changed, number of units has increased and estima

Location, Land & Connectivity

Located at JOGESHWARI EAST, NATWAR NAGAR ROAD NO. 2, Andheri, Mumbai Suburban, 400060. Per the filed land record, the plot is bounded to the north by NATWAR NAGAR ROAD NO 2, to the south by PLOT NO 8, to the east by PLOT NO 16 and to the west by H F SOCIETY ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park6 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Poddar Infracon Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Jogeshwari East

Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises
Avant Heritage - III
possession by Dec 2026 · Avant Heritage III Realty Pvt. Ltd.
Devbhoomi
possession by Dec 2026 · Metro Capital
Iifl Centre
Developer in insolvency (NCLT) · possession by Dec 2026 · Spenta Sun City Private Limited

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

Satyam CHS LTD
declared completion Dec 2021 · Crown Builders & Developers
Satyam CO-Operative Housing Society Limited
possession by Dec 2030 · Jyoti Real-Tech Private Limited
Satyam Solace
possession by Dec 2029 · Satyam Realty
Saujanya Rachanaa
declared completion Dec 2025 · Terraferma Developers LLP
Sayba Arcadia
declared completion Jul 2026 · Star Empire
Sayba Badr
possession by Jun 2029 · Star Shine

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026