MahaRERA Property Intelligence · Raigarh

Savitri Planet

P52000051510 · Pushpak- Vadghar · promoter Savitri Builders And

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP52000051510
Registered on23 Jun 2023
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Savitri Builders And is the promoter of record on 14 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
Savitri Planet1G+631 Dec 2025

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Pushpak- Vadghar, Sector No- R3, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by Plot No- 203B, to the south by 11 M Wide Road, to the east by Plot No-202 and to the west by Plot No-203 and Plot No-203A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Savitri Builders And Developer is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Savitri Builders And Developer project & its RERA track record →

Other flagged projects by Savitri Builders And Developer

Savitri Builders And Developer
FlaggedRaigarh
Savitri Builders And Developer
FlaggedRaigarh

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Savitri Prasad Apartment
declared completion Dec 2021 · Savitri Builders And Developers
Savitri Villa
declared completion Jun 2023 · Ravindra Sadashiv Mahadik
Savli CHS
declared completion Dec 2025 · J M M Homes
Sawan Avenue 2
declared completion Jul 2019 · Shree Sawan Builders & Developers PV
Sawan Majesty
declared completion Jun 2026 · Harnamsingh Kulbirsingh Maker
SD Infra Galaxy
declared completion Mar 2026 · SD Infra Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026