Mumbai/Project record

MahaRERA · the public record

SHAILAJA GPS BUSINESS CENTER

KOHOJ KHUNTAWALI · KPG BUILDERS AND DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2027declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700056487

Delivery and registration

When is the project declared for completion?

SHAILAJA GPS BUSINESS CENTER is registered with MahaRERA as P51700056487 and the promoter has declared completion for 31 Mar 2027.

31 Mar 2027

declared completion

6months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700056487
Registered on05 Jun 2024
Promoter-declared completion31 Mar 2027
Current statusCertificate Signed
Against today6 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHAILAJA GPS BUSINESS CENTER record 9 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 9 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHAILAJA GPS BUSINESS CENTER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHAILAJA GPS BUSINESS CENTER1G+831 Mar 2027

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KOHOJ KHUNTAWALI, STATION ROAD, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by ROAD, to the south by PLOT NO 29, to the east by PLOT NO 21 and to the west by PLOT NO 23. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Shakti Aura
declared completion Jun 2023 · Shakti Developers
Shalicon Srushti
possession by Dec 2027 · Not Available
Shalimar Co.op HSG SOC LTD
possession by Jun 2027 · Neena Shailesh Paranjape
Shambhu Shankar Residency
possession by Dec 2026 · Vidisha Constructions
Shankar Heights Phase 2 Krishna Wing
declared completion Dec 2018 · Laxmi Kamal Associates
Shankar Heights Phase 4
declared completion Jun 2022 · Laxmi Kamal Associates

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026