MahaRERA Property Intelligence · Mumbai Suburban

SHANTINIKETAN 2 CHS LTD

P51800002261 · Ambivali · promoter Bhalerao Constructions Pvt

Certificate SignedDue 30 Nov 2020

Delivery & Registration

MahaRERA registrationP51800002261
Registered on31 Jul 2017
Promoter-declared completion30 Nov 2020
Current statusCertificate Signed
Against todayabout 68 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Bhalerao Constructions Pvt is the promoter of record on 13 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
SHANTINIKETAN 2 CHS LTD1G+1331 May 2019

Complaints & Orders

4 complaints are on the MahaRERA record for this project, with orders passed in 4. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000005798308/02/2019Arvind sonawane vs S D Bhalerao constructionsorder passed
CC00600000005674430/10/2018LATHA VENKATAKRISHNAN RAO vs SANJAY BHALERAOorder passed
CC00600000008965217/06/2019Prathamesh Gajanan Malgundkar and Bhakti Gajanan Malgundkar vs M/s. S. D. Bhalerao Constructions Pvt. Ltd.order passed
CC00600000008965317/06/2019ALPA VILAS SANKHE AND GAJANAN KASHINATH MALGUNDKAR vs M/s S.D.Bhalerao Constructions Pvt Ltdorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Nov 202030 May 2020We wish to inform you that we have already registered our ongoing project, “Shantiniketan (2) CHS Ltd.”, the project bears RERA registration No. P51800002261. The said Society cons

Location, Land & Connectivity

Located at Ambivali, Kevinpada Road, Thane, Thane, 400058. Per the filed land record, the plot is bounded to the north by Janmanas Building and Jadhavchawl, to the south by Sunjoy View Building, to the east by 30 feet road and to the west by Open plot bearing CTS No 542. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park6 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

S D Bhalerao Constructions PVT LTD is the promoter on 5 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by S D Bhalerao Constructions PVT LTD

S D Bhalerao Constructions PVT LTD
FlaggedMumbai Suburban
S D Bhalerao Constructions PVT LTD
Past its declared completion dateMumbai Suburban
S D Bhalerao Constructions PVT LTD
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Andheri West

Shepherd Horizon
possession by Jul 2026 · Goodbuild India Private Limited
Anutam
possession by Sep 2026 · Truly Highdreams Realtors LLP
Vivan Homes
possession by Dec 2026 · Imprint Estates Pvt Ltd
Alpine Primo
possession by Dec 2026 · Alpine Infraheights LLP
Bella Casa
possession by Dec 2026 · Konark Bella Casa LLP
Hetali Sagar
possession by Dec 2026 · Jayesh Himatlal Pandya

Major developers building in Andheri West

Other RERA-registered projects in Mumbai Suburban

Shantivilla
declared completion Mar 2022 · Rikhav Ashit Shah
Shantprabha CO Operative Housing Society Limited
possession by Jun 2027 · Shantprabha CO Operative Housing Society
Shapoorji Pallonji THE Designate
declared completion Dec 2022 · Behold Space Developers Private Limited
Sharad Apartments CHS LTD
declared completion Apr 2022 · Aakar Constructions
Sharanya
possession by Dec 2026 · M/S Satsang Enterprises
Sharda Heights
declared completion Dec 2018 · Narendra Jagdishprasad Agarwal

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026