Mumbai/Project record

MahaRERA · the public record

SHASTRI NAGAR

Mumbai Suburban · NEWTECH LAND DEVELOPERS PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010602

Delivery and registration

When is the project declared for completion?

SHASTRI NAGAR is registered with MahaRERA as P51800010602 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010602
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHASTRI NAGAR record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHASTRI NAGAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+29.

BuildingWingsFloorsDeclared completion
SHASTRI NAGAR1G+29-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. 3 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Metropolitan Magistrate67005952014Pending
Sessions Court572017Pending
High Court Mumbai9252016Pending

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400101. Per the filed land record, the plot is bounded to the north by LAYOUT PLOT NO 17, to the south by LAYOUT PLOT NO 19, to the east by MHADA LAYOUT BOUNDARY and to the west by PUBLIC LAYOUT ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~12 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ12 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)19 km
Lower Parel / Worli business district27 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kandivali East

Aspire
possession by Oct 2026 · M/s Radheshyam Developers
Grande Edifice
possession by Dec 2026 · V6 Enterprises
Kalpataru Vienta Tower B
possession by Dec 2026 · Kalpataru Retail Ventures Private Limite
Paton Towers
possession by Dec 2026 · Pravin Viram Satra
Building No 3 Wing C Aquila
possession by Dec 2026 · S D Corporation Private Limited
Goldmist CO-Operative Housing Society Limited
possession by Dec 2026 · Samarpan Homes & Developers

Major developers building in Kandivali East

Other RERA-registered projects in Mumbai Suburban

Shastri Nagar Prabhat Chsl Phase II A AND B Wing
declared completion Dec 2025 · Reliable Constructions
Shastri Nagar Prerna C.h.s.ltd
possession by Jun 2027 · Confiable Constructions
Shastri Nagar West View CHS Ltd
declared completion Jun 2026 · Umang Construction Co
Shatrunjay Plaza
declared completion Dec 2024 · Acme Metal Industries Pvt Ltd
Sheetal
possession by Mar 2029 · C H Patil AND Sons Sheetal Project
Sheetal Aniket
possession by Dec 2026 · D.g. Land Developers Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026