Mumbai/Project record

MahaRERA · the public record

Lodha Kandivali Project - Tower 5

Akurli Village · Lodha Developers Limited

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

2units filed as unsoldInventory · 18 September 2026
31 Jul 2026declared completionMahaRERA registration · read 12 Jul 2026
88registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800032605

Delivery and registration

When is the project declared for completion?

Lodha Kandivali Project - Tower 5 is registered with MahaRERA as P51800032605 and the promoter has declared completion for 31 Jul 2026.

31 Jul 2026

declared completion

2months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800032605
Registered on14 Jan 2022
Promoter-declared completion31 Jul 2026
Current statusCertificate Signed
Against todayabout 2 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Lodha Kandivali Project - Tower 5 record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Lodha Kandivali Project - Tower 5, ₹80.42 Cr of a declared ₹81.48 Cr estimated project cost is reported as incurred, about 98.7%, as at the last certified filing with MahaRERA.

98.7%

₹80.42 Cr

of ₹81.48 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Lodha Kandivali Project - Tower 5, 86 of 88 homes filed with MahaRERA are recorded as sold or booked, about 98%, and 2 remain available.

98%sold

86 of 88 homes

₹156.46 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹138.03 Cr (about 88%) is recorded as collected and ₹18.43 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 86 registered agreements, the effective carpet rate is ₹26,434/sqft, with eight in ten falling between ₹25,056 and ₹28,293 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Ground/Floor 0003507 sqft (47.1 sqm)₹71.60 Lakh
Ground/Floor 0003A371 sqft (34.47 sqm)₹52.39 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 18 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 86 homes carry one, and 2 of the 88 are recorded unsold.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Lodha Kandivali Project - Tower 5, 0 of the 2 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 2 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22 and 88 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Lodha Kandivali Project - Tower 51G+2288-

Unit mix on the filing: 88 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2026We have already uploaded the Full Occupancy Certificate dated 23th Sep 2025 on the MahaRERA portal for your kind reference. However, the project is currently reflecting under the c

Location, Land & Connectivity

Located at Akurli Village, Akurli Road, Mumbai City, Mumbai City, 400101. Per the filed land record, the plot is bounded to the north by P H Housing, to the south by Akurli Road, to the east by D P Road and to the west by I 3 Zone. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Lodha Developers Limited is the promoter on 134 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Lodha Developers Limited project & its RERA track record →

Other flagged projects by Lodha Developers Limited

Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedMumbai Suburban
Lodha Developers Limited
FlaggedThane
Lodha Developers Limited
FlaggedRaigarh
Lodha Developers Limited
FlaggedRaigarh

Other RERA-registered projects in Kandivali East

Aspire
possession by Oct 2026 · M/s Radheshyam Developers
Grande Edifice
possession by Dec 2026 · V6 Enterprises
Kalpataru Vienta Tower B
possession by Dec 2026 · Kalpataru Retail Ventures Private Limite
Paton Towers
possession by Dec 2026 · Pravin Viram Satra
Building No 3 Wing C Aquila
possession by Dec 2026 · S D Corporation Private Limited
Goldmist CO-Operative Housing Society Limited
possession by Dec 2026 · Samarpan Homes & Developers

Major developers building in Kandivali East

Other RERA-registered projects in Mumbai Suburban

Lodha Mulund Project Tower 1
possession by Sep 2027 · Lodha Developers Limited
Lodha Vikhroli-Signet
possession by Jun 2028 · Lodha Developers Limited
Lodha Vikhroli - Tower C1
possession by Dec 2028 · Lodha Developers Limited
Lodha Woods - Tower 6
possession by Nov 2027 · Lodha Developers Limited
Lodha Woods - Tower 7
possession by Jul 2027 · Lodha Developers Limited
Lodha Woods- Tower 8
possession by Nov 2028 · Lodha Developers Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026