MahaRERA Property Intelligence · Palghar

SHEETAL SONA

P99000020654 · VIRAR EAST · promoter Township Private Limited

Certificate SignedDue 31 May 2025

Delivery & Registration

MahaRERA registrationP99000020654
Registered on30 Apr 2019
Promoter-declared completion31 May 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Township Private Limited is the promoter of record on 111 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
SHEETAL SONA A AND B WING1G+2031 Mar 2022

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250264831/07/2025Sunil Lahange vs D.G.S TOWNSHIP PRIVATE LIMITEDorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202331 May 2025We have completed our project and we are under Process of getting Occupancy Certificate so we need extension till 31 st may 2025
30 Mar 202301 Mar 2024Due to Covid -19 Pandemic the constrction work was stopped for more than 10 months caused delaying in the project.

Location, Land & Connectivity

Located at VIRAR EAST, VIRAR NALASOPARA LINK ROAD, Borivali, Mumbai Suburban, 401305. Per the filed land record, the plot is bounded to the north by s no 240, to the south by d p road, to the east by d p road and to the west by s no 384 385. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

D.g.s Township Private Limited is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by D.g.s Township Private Limited

D.g.s Township Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Virar East

Gajanan Residency
possession by Aug 2026 · Pranita Pankaj Thakur
Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Devi Krupa
possession by Dec 2026 · Vira Links LLP
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon

Other RERA-registered projects in Palghar

Sheetal Yash
possession by Dec 2030 · DGS Builders AND Developers
Shelter Heights
declared completion Dec 2019 · Shree Vimalnath Reality
Shilpa Mansi Darshan
declared completion Dec 2023 · Shilpa Developers
Shirke Apartment
declared completion Mar 2024 · Shree Radhakrishna Developers
Shiv Darshan
declared completion Apr 2022 · M/s. Prathmesh Builders & Developers
Shiv Darshan Apartment
possession by Dec 2026 · Real City Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026