MahaRERA Property Intelligence · Thane

SHREEJI LANDMARK PHASE I

P51700052093 · Shirgaon, Taluka - Ambernath, Badlapur (West) · promoter Shreeji Buildcon

Certificate SignedDue 31 Dec 2027

Delivery & Registration

MahaRERA registrationP51700052093
Registered on24 Jul 2023
Promoter-declared completion31 Dec 2027
Current statusCertificate Signed
Against today17 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shreeji Buildcon is the promoter of record on 141 projects, of which 11 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~57.5% of the estimated project cost incurred as of the last certificate (₹9.25 Cr spent against a ₹16.08 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 89 homes filed with MahaRERA, 20 are sold/booked and 69 remain available (~22% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹7.47 Cr in agreement value so far. Of that, ₹4.17 Cr (~56%) is already collected, ₹3.30 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 20 registered agreements, the effective carpet rate is ₹8,387/sqft (typical range ₹7,390–₹9,441) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 89 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Shreeji Landmark Phase I A Wing1G+1489-

Unit mix on the filing: 82 residential and 7 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Shirgaon, Taluka - Ambernath, Badlapur (West), Survey No 136, Hissa No. 3, , Ambarnath, Thane, 421503. Per the filed land record, the plot is bounded to the north by Property bearing Survey No 136 Hissa No 2, to the south by Property bearing Survey No 136 Hissa No 4, to the east by 100 fts Road and to the west by Remaining Land Bearing Survey No 136 Hissa No 3. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shreeji Buildcon is the promoter on 5 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shreeji Buildcon

Shreeji Buildcon
Not filing quarterly progress reportsThane

Other RERA-registered projects in Badlapur

Ekdant Pooja Chsl
possession by Jul 2026 · Landmark Infra
OM Shiv Darshan
possession by Jul 2026 · Vinayak Enterprises Developers
RAJ Silverstone Phase-2
possession by Jul 2026 · Skyspace Builtek
Sairaj Avenue Wing B
possession by Jul 2026 · Virendra Atmaram Salunkhe
Satyam Sheela Wing F
possession by Jul 2026 · Shreeji Developers
Shreeji Greens
possession by Jul 2026 · Deep Laxmi Associates

Major developers building in Badlapur

Other RERA-registered projects in Thane

Shreeji Landmark Phase II
possession by Dec 2026 · Shubh Housing
Shreeji Meadows
possession by Jul 2026 · Deeplaxmi Developers
Shreeji Milestone
possession by Jun 2029 · Deep Laxmi Associates
Shreeji Nisarg Phase I
declared completion Dec 2022 · Shreeji Developers
Shreeji NX
declared completion Jun 2026 · Shree Ganeshkrupa Construction
Shreeji NX
possession by Dec 2026 · Shubh Builders

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026