MahaRERA Property Intelligence · Mumbai Suburban
P51800008231 · promoter Shreenath Buildgrand Private
| MahaRERA registration | P51800008231 |
| Registered on | 18 Aug 2017 |
| Promoter-declared completion | 30 Sep 2022 |
| Current status | Certificate Signed |
| Against today | about 46 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| SHREENATH DARSHAN | 1 | G+20 | - |
24 complaints are on the MahaRERA record for this project, with orders passed in 24. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC006000000078329 | 20/03/2019 | Motilal Vyas and Rakeshkumar Vyas vs Shreenath Buildgrand Private Limited | order passed |
| CC006000000023092 | 20/02/2018 | Mahanand R Singh vs 1) M/s. Shreenath Builder Grand Pvt. Ltd & 3 ORS | order passed |
| CC006000000023167 | 20/02/2018 | MR. NAVIN MAHANAND SINGH vs M/s. SHREENATH BUILD GRAND PVT. LTD. and 3 others. | order passed |
| CC006000000023168 | 20/02/2018 | MR. SACHIN MAHANAND SINGH vs M/S. SHREENATH BUID GRAND PVT. LTD. and 3 others | order passed |
| CC006000000057024 | 28/11/2018 | MR. SAMEER J. DOSHI AND MR. YOGESH GOSRANI vs SHREENATH BUID GRAND PVT. LTD. | order passed |
| CC006000000023491 | 24/02/2018 | Balendra Arjun Singh And Vishnu Mahadev Shinde vs M/s Shreenath Buildgrand Pvt Ltd, Mr. Niraj Mansukhlal Ved, Sapna Niraj Ved, Bharat Satra | order passed |
| CC006000000057596 | 08/01/2019 | SATISH NATHULAL DOSHI vs Mr. Niraj Mansukhlal Ved | order passed |
| CC006000000078841 | 10/04/2019 | Pravin Shah vs SREENATH BUILD GRAND PVT LTD | order passed |
| CC006000000079404 | 22/05/2019 | Bhagchand Maheshwari , Priyanka Pednekar vs Shreenath Build Grand Private Limited, Niraj Ved, Sapna Ved, Bharat Satra | order passed |
| CC006000000110679 | 27/08/2019 | VINAYAK N HIREMATH vs NIRAJ MANSUKLAL VED | order passed |
| CC006000000110707 | 27/08/2019 | DHARAMBIR SINGH JPHAR vs NEERSJ MANSUSKHLAL VED | order passed |
| CC006000000110709 | 27/08/2019 | CHADRAKANT LAXMAN PATIL vs NEERAJ MANSUKHLAL VED | order passed |
| CC006000000110710 | 27/08/2019 | VELLADURAI N. MANI NADAR vs NEERAJ MANSUKHLAL VED | order passed |
| CC006000000110711 | 27/08/2019 | SUHAS SOPAN JADHAV vs NEERAJ MANSUKHLAL VED | order passed |
| CC006000000110712 | 27/08/2019 | NANDA Y. SAPKALE vs NEERAJ MANSUKHLAL VED | order passed |
| CC006000000110713 | 27/08/2019 | RAJIV DAMAJI GANGAR vs NEERAJ MANSUKHLAL VED | order passed |
| CC006000000110714 | 27/08/2019 | P. RAJKUMAR NADAR vs NEERAJ MANSUKHLAL VED | order passed |
| CC006000000198437 | 01/10/2021 | YATIN BHUPENDRA KHARA vs SHREENATH BUILDGRAND PRIVATE LIMITED | order passed |
| CC006000000197088 | 27/05/2021 | Akbar Ali A Dingankar vs Niraj Mansukhlal Ved | order passed |
| CC006000000262031 | 09/08/2022 | HEMLATA MAHANAND SINGH vs SHREENATH BUILD GRAND PVT. LTD. | order passed |
| CC006000000303345 | 23/11/2022 | Umendra Nath Chaturvedi and Praveen Gopal Chaturvedi vs Shreenath Buildgrand Pvt Ltd | order passed |
| CC006000000303352 | 23/11/2022 | Umendra Nath Chaturvedi and Praveen Gopal Chaturvedi vs Shreenath Buildgrand Pvt Ltd | order passed |
| CC006000000303353 | 23/11/2022 | Umendra Chaturvedi and Gopal Chaturvedi vs Shreenath Buildgrand Pvt Ltd | order passed |
| CC006000000396869 | 29/07/2023 | Mugatlal Bhagwandas Boda and Co vs Shreenath Build Grand Pvt Ltd | order passed |
The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Sep 2022 | 30 Sep 2022 | Plan will amended further as per Reg. 33(11) of DCPR 2034 |
| 30 Sep 2022 | 30 Apr 2020 | Due to Change in DCR 1991 we need to amend the plans as per new DCPR 2034. |
| 30 Sep 2022 | 10 Sep 2021 | Plan Amended as per new DCPR 2034. |
Located at Mumbai City, Mumbai City, 400078. Per the filed land record, the plot is bounded to the north by by open space and chawl no 3, to the south by by bombay agra road, to the east by by property belonging to friends properties and to the west by by public road leading to vihar lake. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.
| Landmark | Straight-line |
|---|---|
| Bandra Kurla Complex (BKC) | 2 km |
| Chhatrapati Shivaji Int'l Airport | 4 km |
| Powai / Hiranandani business park | 7 km |
| Andheri MIDC / SEEPZ | 8 km |
| Lower Parel / Worli business district | 9 km |
| Nariman Point / Fort | 16 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Shreenath Darshan?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026