Shreenath Darshan

P51800008231 · promoter Shreenath Buildgrand Private

Certificate SignedDue 30 Sep 2022

Delivery & Registration

MahaRERA registrationP51800008231
Registered on18 Aug 2017
Promoter-declared completion30 Sep 2022
Current statusCertificate Signed
Against todayabout 46 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
SHREENATH DARSHAN1G+20-

Complaints & Orders

24 complaints are on the MahaRERA record for this project, with orders passed in 24. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000007832920/03/2019Motilal Vyas and Rakeshkumar Vyas vs Shreenath Buildgrand Private Limitedorder passed
CC00600000002309220/02/2018Mahanand R Singh vs 1) M/s. Shreenath Builder Grand Pvt. Ltd & 3 ORSorder passed
CC00600000002316720/02/2018MR. NAVIN MAHANAND SINGH vs M/s. SHREENATH BUILD GRAND PVT. LTD. and 3 others.order passed
CC00600000002316820/02/2018MR. SACHIN MAHANAND SINGH vs M/S. SHREENATH BUID GRAND PVT. LTD. and 3 othersorder passed
CC00600000005702428/11/2018MR. SAMEER J. DOSHI AND MR. YOGESH GOSRANI vs SHREENATH BUID GRAND PVT. LTD.order passed
CC00600000002349124/02/2018Balendra Arjun Singh And Vishnu Mahadev Shinde vs M/s Shreenath Buildgrand Pvt Ltd, Mr. Niraj Mansukhlal Ved, Sapna Niraj Ved, Bharat Satraorder passed
CC00600000005759608/01/2019SATISH NATHULAL DOSHI vs Mr. Niraj Mansukhlal Vedorder passed
CC00600000007884110/04/2019Pravin Shah vs SREENATH BUILD GRAND PVT LTDorder passed
CC00600000007940422/05/2019Bhagchand Maheshwari , Priyanka Pednekar vs Shreenath Build Grand Private Limited, Niraj Ved, Sapna Ved, Bharat Satraorder passed
CC00600000011067927/08/2019VINAYAK N HIREMATH vs NIRAJ MANSUKLAL VEDorder passed
CC00600000011070727/08/2019DHARAMBIR SINGH JPHAR vs NEERSJ MANSUSKHLAL VEDorder passed
CC00600000011070927/08/2019CHADRAKANT LAXMAN PATIL vs NEERAJ MANSUKHLAL VEDorder passed
CC00600000011071027/08/2019VELLADURAI N. MANI NADAR vs NEERAJ MANSUKHLAL VEDorder passed
CC00600000011071127/08/2019SUHAS SOPAN JADHAV vs NEERAJ MANSUKHLAL VEDorder passed
CC00600000011071227/08/2019NANDA Y. SAPKALE vs NEERAJ MANSUKHLAL VEDorder passed
CC00600000011071327/08/2019RAJIV DAMAJI GANGAR vs NEERAJ MANSUKHLAL VEDorder passed
CC00600000011071427/08/2019P. RAJKUMAR NADAR vs NEERAJ MANSUKHLAL VEDorder passed
CC00600000019843701/10/2021YATIN BHUPENDRA KHARA vs SHREENATH BUILDGRAND PRIVATE LIMITEDorder passed
CC00600000019708827/05/2021Akbar Ali A Dingankar vs Niraj Mansukhlal Vedorder passed
CC00600000026203109/08/2022HEMLATA MAHANAND SINGH vs SHREENATH BUILD GRAND PVT. LTD.order passed
CC00600000030334523/11/2022Umendra Nath Chaturvedi and Praveen Gopal Chaturvedi vs Shreenath Buildgrand Pvt Ltdorder passed
CC00600000030335223/11/2022Umendra Nath Chaturvedi and Praveen Gopal Chaturvedi vs Shreenath Buildgrand Pvt Ltdorder passed
CC00600000030335323/11/2022Umendra Chaturvedi and Gopal Chaturvedi vs Shreenath Buildgrand Pvt Ltdorder passed
CC00600000039686929/07/2023Mugatlal Bhagwandas Boda and Co vs Shreenath Build Grand Pvt Ltdorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202230 Sep 2022Plan will amended further as per Reg. 33(11) of DCPR 2034
30 Sep 202230 Apr 2020Due to Change in DCR 1991 we need to amend the plans as per new DCPR 2034.
30 Sep 202210 Sep 2021Plan Amended as per new DCPR 2034.

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400078. Per the filed land record, the plot is bounded to the north by by open space and chawl no 3, to the south by by bombay agra road, to the east by by property belonging to friends properties and to the west by by public road leading to vihar lake. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)2 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district9 km
Nariman Point / Fort16 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhandup West

Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Primo
possession by Sep 2026 · Ceear Land Developers LLP
Aureate
possession by Dec 2026 · Beauty Ganraj Construction LLP
Fairmont
possession by Dec 2026 · Trident Ozone LLP
Neptune Eleve Wing A
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private
Neptune Eleve Wing B
Developer in insolvency (NCLT) · possession by Dec 2026 · Neptune Ventures AND Developers Private

Major developers building in Bhandup West

Other RERA-registered projects in Mumbai Suburban

Shreenath Enclave
declared completion Nov 2025 · Shreenathji Infracon Build Pvt. Ltd.
Shreenath Pride
declared completion Mar 2025 · Ms Shreenath Reality LLP
Shreenath Regency
possession by Oct 2027 · Shreenathji Infracon Build Private Limit
Shreenaths Legacy
declared completion Jul 2024 · Mehul Kirit Mehta
Shreeyog Chsl
declared completion Jun 2023 · Kosmos Developers
Shresth Accord AND Avenue Phase 1
declared completion Dec 2023 · Shresth Lifestyleinfra Developers PVT LT

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026