MahaRERA Property Intelligence · Palghar

SHRIKRISHNA HERITAGE

P99000009732 · promoter Shrikrishna Ventures

Certificate SignedDue 31 May 2018

Delivery & Registration

MahaRERA registrationP99000009732
Registered on22 Aug 2017
Promoter-declared completion31 May 2018
Current statusCertificate Signed
Against todayabout 98 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shrikrishna Ventures is the promoter of record on 31 projects, of which 5 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO 71G+4-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Palghar, Palghar, 401403. Per the filed land record, the plot is bounded to the north by S N 413-1, to the south by S N 412, to the east by S N 413-3-2 and to the west by S N 413-2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~63 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ63 km
Powai / Hiranandani business park65 km
Chhatrapati Shivaji Int'l Airport67 km
Bandra Kurla Complex (BKC)70 km
Lower Parel / Worli business district77 km
Nariman Point / Fort84 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shrikrishna Ventures is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Shrikrishna Ventures

Shrikrishna Ventures
Past its declared completion datePalghar

Other RERA-registered projects in Manor

15 Manor - Belvedere 2
possession by Dec 2026 · RV Infra
Myzo Suites
possession by Dec 2027 · Myzo Infra Private Limited
Myzo Suites Building NO 3 - A Wing
Not filing quarterly progress reports · possession by Dec 2027 · Ayush Reality
Godrej Country Estate
declared completion Apr 2026 · Godrej Projects Development Limited
Bandhan Heritage Phase II
Not filing quarterly progress reports · declared completion Dec 2025 · Mahi Links
Riddhi Siddhi Park Phase-2
Past its declared completion date · declared completion Jun 2024 · Riddhi Siddhi Builders

Other RERA-registered projects in Palghar

Shrikrishna Heritage B AND C Wing
declared completion Dec 2023 · Shrikrishna Ventures
Shrinathji Heights
declared completion Dec 2019 · Shrinathji Builder AND Developers
Shripal Crown Chsl
possession by Dec 2028 · Unnati Constructions
Shripal ONE
declared completion Feb 2025 · Shripal Homes LLP
Shripal Sattva - Bldg. 1
possession by Dec 2027 · Shripal Sattva LLP
Shripal Sattva Bldg. 2
possession by Dec 2028 · Shripal Sattva LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026