MahaRERA Property Intelligence · Mumbai Suburban

SHRISTI RESIDENCY - PHASE 1

P51800031167 · JOGESHWARI EAST · promoter Ranbir Real Estate

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800031167
Registered on11 Oct 2021
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Ranbir Real Estate is the promoter of record on 3 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~108.6% of the estimated project cost incurred as of the last certificate (₹69.32 Cr spent against a ₹63.85 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 221 homes filed with MahaRERA, 170 are sold/booked and 51 remain available (~77% sold) — selling steadily. Buyers have committed ₹182.52 Cr in agreement value so far. Of that, ₹168.76 Cr (~92%) is already collected, ₹13.76 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 170 registered agreements, the effective carpet rate is ₹20,271/sqft (typical range ₹17,889–₹22,785) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18 and 221 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SHRISTI RESIDENCY - WING A1G+1876-
SHRISTI RESIDENCY - WING B1G+1871-
SHRISTI RESIDENCY - WING C1G+1874-

Unit mix on the filing: 215 residential and 6 non-residential (shops/offices).

Complaints & Orders

37 complaints are on the MahaRERA record for this project, with orders passed in 33. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1260091619/02/2026AMITA HIRIYANNA NAYAK vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260000101/01/2026Karandeep Singh Sethi vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1250461624/12/2025Jaya Sunil Apte vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260000701/01/2026Sneha Devadiga vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260002702/01/2026SARITA NAVIN DSOUZA vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260013508/01/2026Karuna Kailas Panchal vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260014709/01/2026Deepika Pradeep Pathak vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260030416/01/2026Rohan Jagannath Raut vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260076010/02/2026Saurabh Shaileshkumar Salunkhe vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260040021/01/2026Pamela Peter Cardoz vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260041922/01/2026Jaspreetsingh H Chandhok vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260046826/01/2026SACHIN NANDKUMAR NAIK vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260066905/02/2026Anuja Mahesh Rahatwal vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260075710/02/2026Henry Jerome Dsouza vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260073709/02/2026Santosh Dhondu Pawar vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260075109/02/2026Swati Subodh Bagwe vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260077310/02/2026Dashrath Vasudev Bagwe vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260099624/02/2026Vinayak Sahadeo Haryan vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260087016/02/2026Anjali Mohanlal Jain vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260087617/02/2026Bruna Maria Dsouza vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260090119/02/2026Bautis Peter Fernandes vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260092819/02/2026Akshata Anil Redekar vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260093119/02/2026Rajesh Dilip Labde vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260094620/02/2026Shailesh Dilip Labde vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260095921/02/2026Prashant Sudam Ahire vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260112702/03/2026Shivani Bhikaji Ghag vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260125608/03/2026PREMANAND PANDHARINATH MESTRY vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260135112/03/2026VISHAL PRADEEP TAMBE vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260129710/03/2026Vimal Dinesh Dodhia vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260135612/03/2026Maruti Bhau Jangam vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260144615/03/2026Sonali Amit Shikhare vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260148917/03/2026Manoj Shrikant Mahajan vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260149118/03/2026Prashant Prabhakar Brid vs RANBIR REAL ESTATE AND DEVELOPERS LLPorder passed
CC1260238122/04/2026Shantaram Laxman Shinde vs RANBIR REAL ESTATE AND DEVELOPERS LLPpending / no order on file
CC1260314126/05/2026Amol Dashrath Shelar vs RANBIR REAL ESTATE AND DEVELOPERS LLPpending / no order on file
CC1260400627/06/2026Kishorkumar Chandraprakash Duratkar vs RANBIR REAL ESTATE AND DEVELOPERS LLPpending / no order on file
CC1260401127/06/2026Ponsil Kanakraj Nadar vs RANBIR REAL ESTATE AND DEVELOPERS LLPpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202430 Dec 2025UNFORESEEN CIRCUMSTANCES THE PROJECT WAS NOT ABLE TO GET COMPLETED IN TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENTION TILL 31ST DECEMBER 2025.
31 Dec 202431 Dec 2026The project was delayed due to an unavoidable reason that was beyond our control. Maily the road work process and other work was hampered. We requested the extension as per order 4

Location, Land & Connectivity

Located at JOGESHWARI EAST, C.T.S No. 156 (part), 160/A/1 (part) and 162 (part) of Village Majas situate, lying and being at Meghwadi, Sarvoday Nagar Road, Jogeshwari (East), Mumbai-400 060 , Andheri, Mumbai Suburban, 400060. Per the filed land record, the plot is bounded to the north by 18 PT 30 M WIDE PROPOSED DP ROAD, to the south by 13 PT 40 M WIDE EXISTING JIJAMATA ROAD, to the east by 18 PT 30 M WIDE EXISTING DP ROAD and to the west by ADJOINING BEST BUS STATION. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~1 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ1 km
Powai / Hiranandani business park5 km
Chhatrapati Shivaji Int'l Airport5 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari East

Rose Blossom Chsl
possession by Aug 2026 · Vini Developers
Satyam
possession by Aug 2026 · Poddar Infracon Private Limited
Samarpan
possession by Sep 2026 · L K Infracon LLP
Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

Shubh
possession by May 2029 · Elite Lifespaces
Shubh Aangan
declared completion Jun 2022 · G D Realtors PVT LTD
Shubh Aangan Wing B
declared completion Dec 2023 · G D Realtors PVT LTD
Shubh Aashish
declared completion Dec 2019 · A B Builder & Developers PVT LTD
Shubh Bhaktas Tower
declared completion Dec 2022 · Thackorbhai Gokalbhai Bhakta
Shubh Chintan
declared completion Jun 2022 · AUM Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026