MahaRERA Property Intelligence · Thane

SHUBHAM HEIGHT

P51700017315 · KALYAN EAST · promoter Gauri Vinayak Builder

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51700017315
Registered on07 Aug 2018
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SHUBHAM HEIGHT1G+531 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at KALYAN EAST, TISGAON, Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by DALVI AND GAIKWAD PROPERTY, to the south by GANESH GAIKWAD, to the east by VILLAGE BOUNDRY KATEMANIVALI and to the west by 18M ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Gauri Vinayak Builder And Developers Pvt Ltd is the promoter on 12 MahaRERA-registered projects, of which 6 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Gauri Vinayak Builder And Developers Pvt Ltd project & its RERA track record →

Other flagged projects by Gauri Vinayak Builder And Developers Pvt Ltd

Gauri Vinayak Builder And Developers Pvt Ltd
FlaggedThane
Gauri Vinayak Builder And Developers Pvt Ltd
FlaggedThane
Gauri Vinayak Builder And Developers Pvt Ltd
Past its declared completion dateThane
Gauri Vinayak Builder And Developers Pvt Ltd
Past its declared completion dateThane
Gauri Vinayak Builder And Developers Pvt Ltd
FlaggedThane
Gauri Vinayak Builder And Developers Pvt Ltd
Past its declared completion dateThane

Other RERA-registered projects in Kalyan East

Krishna Square
possession by Jul 2026 · Gopal Krishna Developers
SAI Heights
possession by Aug 2026 · Aaradhana Construction
Avighna Karan Wing C
possession by Aug 2026 · Avighna Karan
Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Durga Imperial
possession by Oct 2026 · G K Mali & C K Mali

Major developers building in Kalyan East

Other RERA-registered projects in Thane

Shubham Heights
declared completion Dec 2022 · Shyamsunder Radhyshyam Agrawal
Shubham Heights
declared completion Dec 2024 · Shubham Builders AND Developers
Shubham Krupa
declared completion Jul 2025 · Shree Samarth Developers
Shubham Monolith
declared completion May 2024 · Gauri Vinayak Builder And Developers Pvt
Shubham Monolith D Wing
possession by Dec 2026 · Gauri Vinayak Builder And Developers Pvt
Shubham Paradise Abcdef Wing
declared completion Feb 2022 · Gauri Vinayak Builder And Developers Pvt

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026