Mumbai/Project record

MahaRERA · the public record

SILVER ARCADE

Thane · SIDDHIVINAYAK ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700009261

Delivery and registration

When is the project declared for completion?

SILVER ARCADE is registered with MahaRERA as P51700009261 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700009261
Registered on22 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SILVER ARCADE record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SILVER ARCADE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SILVER ARCADE1G+831 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Thane, Thane, Thane, 400601. Per the filed land record, the plot is bounded to the north by CTS NO 66, to the south by LODHA COMLEX, to the east by CTS NO 57 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park13 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Siddhivinayak Enterprises is the promoter on 9 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Siddhivinayak Enterprises project & its RERA track record →

Other flagged projects by Siddhivinayak Enterprises

Siddhivinayak Enterprises
Past its declared completion dateThane
Siddhivinayak Enterprises
FlaggedThane

Other RERA-registered projects in Thane

Avesa
possession by Oct 2026 · Jagdale Infrastructure Pvt. Ltd.
Ramashankar CHS LTD
possession by Oct 2026 · SAI Prasad Builders AND Developers
Bhavana Apartment CHS
possession by Nov 2026 · Shree Infra
Sheth Zuri
possession by Dec 2026 · Sheth Developers Private Limited
Musica Apartment
possession by Dec 2026 · E I Construction
Rustomjee LA Familia - Wing A
possession by Dec 2026 · Kapstone Constructions Private Limited

Major developers building in Thane

Other RERA-registered projects in Thane

Silver Bliss
possession by Jun 2027 · Bhushan Balkrishna Bandre
Silver Creast B Wing
declared completion May 2023 · Shrikrishna Enterprises
Silver Crest
possession by Dec 2028 · Akhitech Realty
Silver Lifestyle
possession by Dec 2026 · Silverline Buildheight LLP
Silver Line Phase - 1
possession by Mar 2031 · Home Consultancy
Silver OAK Apartment
declared completion Mar 2025 · Ashokkumar Topanlal Dewani

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026