Mumbai/Project record

MahaRERA · the public record

SIMANDHAR

Bhuleshwar, Chira Bazar · MANSUKH POPATLAL SHAH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900013585

Delivery and registration

When is the project declared for completion?

SIMANDHAR is registered with MahaRERA as P51900013585 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900013585
Registered on16 Oct 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SIMANDHAR record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Mansukh Popatlal Shah is the promoter of record on 11 projects registered with MahaRERA, 3 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

3flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SIMANDHAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
SIMANDHAR1G+2230 Mar 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2018The project has got delayed because flat interior works are pending which we were expecting to complete by 31st December, 2017. As per the current scenario of working we expect tha
31 Dec 201830 Sep 2021The delay of the project was due to no permission from BMC for construction. We applied to rise of floors from 18th to 22nd and moreover new DCR 2034 rules were also going to come
30 Sep 202131 Mar 2024As as per regulatory order 32 extension has been sanctioned upto 31.3.24.

Location, Land & Connectivity

Located at Bhuleshwar, Chira Bazar, Division at 395-399, J.S.S. Road , Ward ABCD, Mumbai City, 400002. Per the filed land record, the plot is bounded to the north by CS NO 1964, to the south by CS NO 1962, to the east by CS NO 1986 and to the west by JSS ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Nariman Point / Fort3 km
Lower Parel / Worli business district5 km
Bandra Kurla Complex (BKC)14 km
Chhatrapati Shivaji Int'l Airport16 km
Powai / Hiranandani business park21 km
Andheri MIDC / SEEPZ21 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhuleshwar

Lifescapes Kshitij
Developer in insolvency (NCLT) · possession by Nov 2026 · Roxina Real Estate Pvt. Ltd.
Krishvi Escape
possession by Dec 2026 · Shagun Realty
Soutth Bay
possession by Dec 2026 · M/s. Sambhav Shelters
Ocean Drive
possession by Mar 2027 · Atul Projects GK Private Limited
Ajmera Downtown
possession by Dec 2027 · Ashjit Realties Pvt. Ltd.
Aryam
possession by Dec 2027 · Myra Infrastructure

Major developers building in Bhuleshwar

Other RERA-registered projects in Mumbai City

SKY 27
possession by Dec 2028 · Space Developers
Sky 9
possession by May 2029 · Mitani Realtors LLP
Sky Crest 8
possession by Dec 2031 · Maanveer Enterprises LLP
Skye 31
possession by Jul 2028 · B P Gangar Constructions Pvt Ltd
SM Royale
possession by Mar 2029 · S M Builderrs AND Developerrs
SNS Heights
declared completion Dec 2024 · Landmark Realty Developer

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026