SOLITAIRE

P51800008101 · Somwari Bazar · promoter Solitaire Constructions

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51800008101
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Solitaire Constructions is the promoter of record on 12 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~100.0% of the estimated project cost incurred as of the last certificate (₹71.96 Cr spent against a ₹71.96 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 150 homes filed with MahaRERA, 114 are sold/booked and 36 remain available (~76% sold) — selling steadily. Buyers have committed ₹75.68 Cr in agreement value so far. Of that, ₹66.46 Cr (~88%) is already collected, ₹9.22 Cr receivable — a read on how far along these sales really are. Note: the project registers 156 homes in total, but this sold/unsold inventory filing covers only 150 of them — the other 6 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 114 registered agreements, the effective carpet rate is ₹14,402/sqft (typical range ₹12,615–₹17,100) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1102681 sqft (63.23 sqm)₹1.03 Cr
Floor 1104686 sqft (63.7 sqm)₹1.03 Cr
Floor 1105713 sqft (66.28 sqm)₹1.09 Cr
Floor 1Office No - 11,685 sqft (156.55 sqm)₹2.92 Cr
Floor 131302681 sqft (63.23 sqm)₹1.13 Cr
Floor 141402681 sqft (63.23 sqm)₹1.13 Cr
Floor 151502681 sqft (63.23 sqm)₹1.13 Cr
Floor 161602681 sqft (63.23 sqm)₹1.13 Cr
Floor 171705713 sqft (66.28 sqm)₹1.18 Cr
Floor 181808287 sqft (26.66 sqm)₹47.61 Lakh
Floor 191902287 sqft (26.66 sqm)₹47.61 Lakh
Floor 191903287 sqft (26.66 sqm)₹47.61 Lakh
Floor 191904287 sqft (26.66 sqm)₹47.61 Lakh
Floor 191905713 sqft (66.28 sqm)₹1.24 Cr
Floor 191909287 sqft (26.66 sqm)₹47.61 Lakh
Floor 2202681 sqft (63.23 sqm)₹1.09 Cr
Floor 2204686 sqft (63.7 sqm)₹1.09 Cr
Floor 2205713 sqft (66.28 sqm)₹1.13 Cr
Floor 3302681 sqft (63.23 sqm)₹1.08 Cr
Floor 3305713 sqft (66.28 sqm)₹1.13 Cr
Floor 4402681 sqft (63.23 sqm)₹1.08 Cr
Floor 4404686 sqft (63.7 sqm)₹1.09 Cr
Floor 4405713 sqft (66.28 sqm)₹1.13 Cr
Floor 5502681 sqft (63.23 sqm)₹1.08 Cr
Floor 6602681 sqft (63.23 sqm)₹1.08 Cr
Floor 6604686 sqft (63.7 sqm)₹1.09 Cr
Floor 6605713 sqft (66.28 sqm)₹1.13 Cr
Floor 7703449 sqft (41.67 sqm)₹71.05 Lakh
Floor 8802681 sqft (63.23 sqm)₹1.08 Cr
Floor 9902681 sqft (63.23 sqm)₹1.13 Cr
Ground/Floor 01492 sqft (45.68 sqm)₹97.20 Lakh
Ground/Floor 02286 sqft (26.58 sqm)₹56.55 Lakh
Ground/Floor 03636 sqft (59.13 sqm)₹1.26 Cr
Ground/Floor 04460 sqft (42.74 sqm)₹90.93 Lakh
Ground/Floor 0SHOP NO. 4341 sqft (31.68 sqm)₹67.50 Lakh
Ground/Floor 0SHOP NO. 5292 sqft (27.1 sqm)₹57.70 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+25 and 156 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
OM DATTA KRUPA WELFARE SRA SAHAKARI GRUHANIRMAN SANSTHA MARYADIT1G+2054-
SOLITAIRE HEIGHTS1G+25102-

Unit mix on the filing: 146 residential and 10 non-residential (shops/offices).

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019604919/02/2021Namrata Shinde vs Solitaire Constructionorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Court Dindoshi13172014Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 4 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
15 May 202515 May 2025INITIAL DELAY DUE TO LOCKDOWN NO SUPPLY OF MATERIALS, SERVICES OF CONTRACTOR, ECONOMICAL CONDITION OF REAL ESTATE SECTOR MARKET SLOWDOWN AND PROLONGED DELAY IN OBTAINING NECESSARY
15 May 202530 Sep 2021EXTENDED DUE DATE WAS 30TH SEPTEMBER 2020 , PROMOTER COULD NOT COMPLETE THE PENDING WORK DUE TO VARIETY OF FACTORS MAINLY DUE TO NON-AVAILABILITY OF LABOUR BECAUSE OF COVID SITUAT
15 May 202530 Mar 2020ATTACHED IN OTHER AS PER OTHER ATTACHMENT
31 Mar 201931 Dec 2026We, Solitaire Construnctions, hereby declare the following with respect to the project “SOLITAIRE” bearing registration number P51800008101 registered under MahaRERA 1. Status of W

Location, Land & Connectivity

Located at Somwari Bazar, N.L. Cross Road, Borivali, Mumbai Suburban, 400064. Per the filed land record, the plot is bounded to the north by CTS NO 829 AND 857, to the south by CTS NO 961 AND 853, to the east by CTS NO 829 AND 834 and to the west by CTS NO 921 AND 920. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~7 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ7 km
Powai / Hiranandani business park10 km
Chhatrapati Shivaji Int'l Airport11 km
Bandra Kurla Complex (BKC)13 km
Lower Parel / Worli business district21 km
Nariman Point / Fort29 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Malad West

Ajmera Arham
possession by Jul 2026 · Vishal Construction
Imperial Hava Hira
possession by Jul 2026 · Shree SAI Realty
Liberte64
possession by Aug 2026 · Jadhwani Infrastructure LLP
Ramdev Veeral Heights
possession by Aug 2026 · Ramdev Associates
Rajgopal Building
possession by Sep 2026 · Harmony AND Prosperity Developer
Shree Hari Krupa
possession by Sep 2026 · Mamtora Foundation

Major developers building in Malad West

Other RERA-registered projects in Mumbai Suburban

Solitaire
declared completion Dec 2017 · Rajendra Pundlikrao Godshalwar
Solitaire Aawas
declared completion Dec 2024 · Sanket Realtors
Solitaire Business Park
declared completion Dec 2021 · Crescent Realty Developers Private Limit
Solitaire Edge
possession by Dec 2026 · Mahaveer Construction
Solitaire II
declared completion Dec 2018 · Tulsi Enterprise Joint Venture
Solitaire Sardar Ugam Sadan
possession by Dec 2028 · Solitaire Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.