Mumbai/Project record

MahaRERA · the public record

SONA PARADISE

Thane · SONA ENTERPRISES

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008053

Delivery and registration

When is the project declared for completion?

SONA PARADISE is registered with MahaRERA as P51700008053 and the promoter has declared completion for 31 Dec 2025.

31 Dec 2025

declared completion

9months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008053
Registered on18 Aug 2017
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 9 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SONA PARADISE record 34 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Sona Enterprises is the promoter of record on 66 projects registered with MahaRERA, 11 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

66projects

registered with MahaRERA

11flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SONA PARADISE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SONA PARADISE1G+730 Dec 2018

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for SONA PARADISE, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000030303/09/2017Nadim Mohammed Ali Chilwan vs Hasmukh Punshi Nisar, Archana waaghmareorder passed
CC00600000000119610/10/2017Afroz Mohammad Ali Chilwan vs Hasmukh Punshi Nisar and Archana Waghmareorder passed
CC00600000000030404/09/2017Gufran Zainuddin khan vs Sona Enterprises (Hasmukh punshi Nihsar/Archana Waghmareorder passed
CC00600000000032029/08/2017VIJAYA POWAR vs M/s.SONA ENTERPRISESorder passed
CC00600000002319302/02/2018ANSARI PARVEZ QAMAR vs Vijaya Powarorder passed
CC00600000001251019/12/2017HASMUKH PUNSHI NISAR vs HASMUKH PUNSHI NISARorder passed

Legal & Litigation

The promoter has declared 3 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Court Thane9242016Hearing
High Court Of Bombay17372018Hearing
High Court Of Bombay324102017Hearing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Apr 2020Sona Paradise Project is a joint venture project which is on 50% - 50% basic between Land Lord and Developer. The Development Agreement and Power of Attorny is made and entered b
30 Apr 202031 Dec 2025Due to financial crisis of previous promoter

Location, Land & Connectivity

Located at Thane, Thane, 421201. Per the filed land record, the plot is bounded to the north by SURVEY NO 121 - 3P, to the south by SURVEY NO 87, to the east by SURVE NO 86 and to the west by SURVEY NO 120. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~22 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park22 km
Andheri MIDC / SEEPZ25 km
Chhatrapati Shivaji Int'l Airport27 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district36 km
Nariman Point / Fort42 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel
Sumati Skyline
possession by Sep 2026 · Subhash Skyline Infra
Vinayak Prerana
possession by Sep 2026 · Nakshatra Group
Shanu Majestic
possession by Dec 2026 · Fortune Group Of Construction
Balaji Annex
possession by Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders

Major developers building in Dombivli East

Other RERA-registered projects in Thane

Sonadevi Heights
declared completion Mar 2022 · Rohit Balaram Choudhari
Sonal CO-OP Housing Society
declared completion Jan 2019 · Soham Developers
Sonal Paradise
possession by Dec 2026 · Shubh Group
Sontakke Building
possession by Feb 2031 · SNA Build-Tech
Sophia Apartment
declared completion Aug 2022 · Aaria Enterprises
Sparrow
declared completion Nov 2018 · Pranjee Properties Pvt. Ltd.

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026