Mumbai/Project record

MahaRERA · the public record

Spee Skytower Wing A and B

Parel · Spee Realtor

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900024490

Delivery and registration

When is the project declared for completion?

Spee Skytower Wing A and B is registered with MahaRERA as P51900024490 and the promoter has declared completion for 30 Mar 2024.

30 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900024490
Registered on18 Feb 2020
Promoter-declared completion30 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Spee Skytower Wing A and B record 17 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Registration revoked — MahaRERA revoked the registration.
  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 17 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Spee Realtor is the promoter of record on 7 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

7projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Spee Skytower Wing A and B in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+2.

BuildingWingsFloorsDeclared completion
Spee Skytower Wing A and B1G+231 Mar 2023

Legal and disputes

What disputes are disclosed?

2 complaints are on the MahaRERA record for Spee Skytower Wing A and B, with orders passed in 2 of them.

2complaints

2with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000025135305/06/2022Shree Bamandeo Co-operative Society (society) vs Spee Realtororder passed
CC00600000054076313/06/2024Manjeet Singh Jawala Singh Alagh vs Spee Realtorsorder passed

A co-operative housing society is recorded as the complainant (Shree Bamandeo Co-operative Society), and MahaRERA has passed an order.

Location, Land & Connectivity

Located at Parel , Jerbai Wadia Road, Haveli, Pune, 400012. Per the filed land record, the plot is bounded to the north by St Xaviers Road, to the south by Jerbai Wadia Road, to the east by Tata Hospital Annex and to the west by 20 Feet Wide Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~110 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Hinjewadi Rajiv Gandhi IT Park110 km
Baner–Balewadi belt115 km
Pune Int'l Airport (Lohegaon)125 km
Pune Junction / city centre125 km
Kharadi / EON IT Park129 km
Magarpatta / Hadapsar IT130 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Parel

Inspire
possession by Sep 2026 · R K Constructions
K RAS Residency
possession by Sep 2026 · K RAS Group
Kinjal Pride
possession by Oct 2026 · Hi Rock Construction Pvt Ltd
Bhivawani Chawl
possession by Dec 2026 · MS Radhakrishna Developer
Bhoiwada Chandra Bhuvan CHS Ltd
possession by Dec 2026 · Avadhoot Techno Consultant And Engineers
Ruparel Jewel
possession by Dec 2026 · Renuka Realtors

Major developers building in Parel

Other RERA-registered projects in Mumbai City

Spenta Nest
possession by Dec 2028 · Shubh Enterprises
Spring Dale
declared completion Sep 2018 · Sunrise Associates
SSG Springville
declared completion Dec 2024 · Itmc Developers Pvt. Ltd.
Stardeous
possession by Dec 2027 · Heston Builders PVT LTD
Stella
declared completion Mar 2019 · Sant Sagar Builders AND Developers Priva
Sterling Luxuria
possession by Jun 2027 · Mohamed Talha Abubakar Momin

What to verify (registration revoked)

  1. Pull the MahaRERA revocation order — it states the reason and effective date. Available on the MahaRERA portal under the project's registration.
  2. Check whether the developer has filed an appeal with the MahaRERA Appellate Tribunal (AT) and whether a stay is in effect.
  3. Stop any further payments until you have legal clarity on the project's status post-revocation.
  4. Consult a RERA advocate about your rights under Section 18 of the Real Estate (Regulation and Development) Act for refund or possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026