Spenta Nest

Mumbai City · Shubh Enterprises

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900012560

Delivery and registration

When is the project declared for completion?

Spenta Nest is registered with MahaRERA as P51900012560 and the promoter has declared completion for 30 Dec 2028.

30 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900012560
Registered on04 Sep 2017
Promoter-declared completion30 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Spenta Nest record 39 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Spenta Nest in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Spenta Nest1G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
High Court Bombay269/20102010In Progress

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by Mancherji Joshi Road, to the south by Jahangir Wadilal Road, to the east by CTS No 573 A10 and to the west by 0. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Lower Parel / Worli business district2 km
Bandra Kurla Complex (BKC)7 km
Nariman Point / Fort9 km
Chhatrapati Shivaji Int'l Airport9 km
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ14 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Shubh Enterprises is the promoter on 5 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Shubh Enterprises project & its RERA track record →

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD
Panchratna-NX
possession by Dec 2026 · Sudhir Kishor Desai

Other RERA-registered projects in Mumbai City

Spring Dale
declared completion Sep 2018 · Sunrise Associates
SSG Springville
declared completion Dec 2024 · Itmc Developers Pvt. Ltd.
Stardeous
possession by Dec 2027 · Heston Builders PVT LTD
Stella
declared completion Mar 2019 · Sant Sagar Builders AND Developers Priva
Sterling Luxuria
possession by Jun 2027 · Mohamed Talha Abubakar Momin
Subodh Sagar
possession by Dec 2027 · Subodh Darshan Associates

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026