SSG Springville

Vikroli · ITMC Developers Pvt. Ltd.

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900017166

Delivery and registration

When is the project declared for completion?

SSG Springville is registered with MahaRERA as P51900017166 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900017166
Registered on17 Jul 2018
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SSG Springville record 26 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 26 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Itmc Developers is the promoter of record on 2 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SSG Springville in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+43.

BuildingWingsFloorsDeclared completion
SSG Springville1G+4331 Dec 2023

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Vikroli, Adishankracharya Marg, Borivali, Mumbai Suburban, 400083. Per the filed land record, the plot is bounded to the north by Adishankracharya Marg, to the south by Seema Stone Co, to the east by 50 wide DP Road and to the west by Narendra Stone Co. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park2 km
Andheri MIDC / SEEPZ6 km
Chhatrapati Shivaji Int'l Airport7 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district17 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Itmc Developers Pvt. Ltd. is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Itmc Developers Pvt. Ltd.

Itmc Developers Pvt. Ltd.
Registration suspendedMumbai Suburban

Other RERA-registered projects in Vikhroli East

Shree Balaji 7
possession by Sep 2026 · Saptrishi Landmarks LLP
Unique Enclave Residency
possession by Sep 2026 · Fazal Shaikh
Vrindavan Elite
possession by Oct 2026 · Matrix Constructions
Meadows 83
possession by Oct 2026 · Shreeji Realtors
Eastern Groves Phase 2
possession by Dec 2026 · VL Savli Developers LLP
GS Casa
possession by Dec 2026 · Prach Realcon LLP

Major developers building in Vikhroli East

Other RERA-registered projects in Mumbai City

Stardeous
possession by Dec 2027 · Heston Builders PVT LTD
Stella
declared completion Mar 2019 · Sant Sagar Builders AND Developers Priva
Sterling Luxuria
possession by Jun 2027 · Mohamed Talha Abubakar Momin
Subodh Sagar
possession by Dec 2027 · Subodh Darshan Associates
Sugan Heights
declared completion Aug 2026 · Gulabdevi Jain & Others
Sugee Paavan
declared completion Sep 2023 · Sugee Seven Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026