MahaRERA Property Intelligence · Mumbai City

Sugee Paavan

P51900022326 · Matunga · promoter Sugee Seven Developers

Certificate SignedDue 30 Sep 2023

Delivery & Registration

MahaRERA registrationP51900022326
Registered on16 Sep 2019
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 34 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sugee Seven Developers is the promoter of record on 23 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+18.

BuildingWingsFloorsDeclared completion
Sugee Paavan1G+1830 Sep 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Matunga, KA Subramanyam Marg, Ward GSouth, Mumbai City, 400019. Per the filed land record, the plot is bounded to the north by Brahman Wada road and plot no 19, to the south by plot no 17 and 19, to the east by Brahman Wada road and plot no 17 and to the west by Plot No 49 and 19. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Matunga

Balkrishna Hills
possession by Sep 2026 · Oriental Contractors Private Limited
Gulraj Paradise
possession by Sep 2026 · M/S Reliable Construction
Signare
Past its declared completion date · possession by Sep 2026 · Tejukaya Buildcon
Chhaya
possession by Dec 2026 · Fortune Realty
Jade Acharya
possession by Dec 2026 · Raghavendra Acharya & Others
Shayona
possession by Dec 2026 · Devesh Narendra Jani

Major developers building in Matunga

Other RERA-registered projects in Mumbai City

Sugee Parimal
declared completion Dec 2023 · Sugee Developers PVT LTD
Sugee Renaissance
possession by Sep 2026 · Sugee Two Developers LLP
Sugee Samruddhi
possession by Aug 2027 · Sugee Six Developers LLP
Sugee Srushti
possession by Oct 2027 · Sugee Fifteen Developers LLP
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
Sukhadwala Mansion
declared completion Mar 2021 · Sisodia Canning PVT LTD

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026