Mumbai/Project record

MahaRERA · the public record

Sugee Samruddhi

Shivaji Park · Sugee Six Developers LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

1units filed as unsoldInventory · 19 September 2026
31 Aug 2027declared completionMahaRERA registration · read 12 Jul 2026
10registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Aug 2027

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900056033

Delivery and registration

When is the project declared for completion?

Sugee Samruddhi is registered with MahaRERA as P51900056033 and the promoter has declared completion for 31 Aug 2027.

31 Aug 2027

declared completion

11months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900056033
Registered on10 May 2024
Promoter-declared completion31 Aug 2027
Current statusCertificate Signed
Against today11 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Sugee Samruddhi record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sugee Six Developers is the promoter of record on 25 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

25projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In Sugee Samruddhi, ₹23.06 Cr of a declared ₹23.22 Cr estimated project cost is reported as incurred, about 99.3%, as at the last certified filing with MahaRERA.

99.3%

₹23.06 Cr

of ₹23.22 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Sugee Samruddhi, 7 of 10 homes filed with MahaRERA are recorded as sold or booked (5 with registered agreements and 2 booked), about 70%, and 3 remain available.

70%sold

7 of 10 homes

₹51.57 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹26.15 Cr (about 51%) is recorded as collected and ₹25.43 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 7 registered agreements, the effective carpet rate is ₹53,161/sqft, with eight in ten falling between ₹41,401 and ₹327,839 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1010011,630 sqft (151.47 sqm)₹5.74 Cr
Floor 1212011,630 sqft (151.47 sqm)₹6.01 Cr
Floor 202004217 sqft (20.12 sqm)₹89.53 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 9 homes carry one, and 1 of the 10 are recorded unsold. Since we started watching this ledger, 2 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
10011,630 sqftRs 7.0625 cr typical, over Rs 6.7500 cr to Rs 8.4500 cr4 filed on this stack, floors 11–18

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Sugee Samruddhi, every one of the 1 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See all 9 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14 and 10 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Sugee Samruddhi1G+1410-

Unit mix on the filing: 10 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Sugee Samruddhi, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
SM1260004010/01/2026Bhakti Achrekar vs Sugee Six Developers LLPorder passed

Location, Land & Connectivity

Located at Shivaji Park, Dr. M.B. Raut Marg, Ward GSouth, Mumbai City, 400028. Per the filed land record, the plot is bounded to the north by 80 feet Road of L J Road, to the south by Plot No 136, to the east by Plot No 172 and to the west by 40 feet Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Sugee Six Developers LLP is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Dadar West

Arihant Tower
possession by Sep 2026 · Mehta Developers
Palette
possession by Sep 2026 · Suraj Estate Developers LTD
Vijayshree
possession by Sep 2026 · Sugee Eighteen Developers LLP
Yash Trinity
possession by Sep 2026 · Bhalchandra Vinayak Wadnerkar
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
1891 Ekam Parkk
possession by Dec 2026 · Nascent Developers

Major developers building in Dadar West

Other RERA-registered projects in Mumbai City

Sugee Srushti
possession by Oct 2027 · Sugee Fifteen Developers LLP
Sugee Sukrut
possession by Oct 2026 · Sugee Nine Developers LLP
Sugee Vrundavan
possession by Dec 2029 · Sugee Developers Private Limited
Sukruti Samyra
possession by Dec 2027 · Posiedon Hotels LLP
Sumati Heights
declared completion Dec 2023 · Tangent Enterprises
Sumer Samaq Prime
declared completion Jun 2026 · Samaq Builders Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026