MahaRERA Property Intelligence · Mumbai Suburban

SRINIVAS BUILDING

P51800010910 · promoter Arjun Development Construction

Certificate SignedDue 30 Jun 2023

Delivery & Registration

MahaRERA registrationP51800010910
Registered on31 Aug 2017
Promoter-declared completion30 Jun 2023
Current statusCertificate Signed
Against todayabout 37 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Arjun Development Construction is the promoter of record on 50 projects, of which 9 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
SRINIVAS BUILDING1G+1531 Dec 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202330 Jun 2022We had applied for Fire NOC to the Chief Fire Officer around September 2020, but were told to make some structural changes. After incorporating those changes final NOC from Chief F
30 Jun 202330 Jun 2023I hereby state that the building under reference is physically complete as per plans approved by the MCGM vide no CHE/ES/0865/M/W/337(NEW). We have also obtained PART OCCUPATION C

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400071. Per the filed land record, the plot is bounded to the north by CTS NO 1278, to the south by CTS NO 1279, to the east by CTS NO 1279 B and to the west by R C MARG. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park7 km
Andheri MIDC / SEEPZ9 km
Lower Parel / Worli business district10 km
Nariman Point / Fort17 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Chembur Deep Jyoti CHS LTD
possession by Jul 2026 · P M Developers
Hubtown Seasons - B Wing
possession by Jul 2026 · Joynest Premises Privatelimited
Gurukripa
possession by Sep 2026 · Inspira Realty And Infra Private Limited
Kranti Heights
possession by Sep 2026 · Sidhivinayak Constructions
Mass Metropolis
possession by Sep 2026 · Grace Urban Development Corporation
Mohite Mrugank
possession by Sep 2026 · Mohite Infraprojects Private Limited

Major developers building in Chembur

Other RERA-registered projects in Mumbai Suburban

Sripad Garden View Co-Op Housing Society Ltd
declared completion Nov 2025 · Sripad Garden View Co-Op Housing Society
Srishti Elegance
declared completion Jun 2019 · Swastik Realtors
Srishti Harmony III- Phase 1
declared completion Dec 2019 · Nathan Properties PVT LTD
Srishti Harmony III- Phase II C Wing
declared completion Jun 2024 · Nathan Properties PVT LTD
Srishti Oasis PH 1 Wing A Palms
declared completion Mar 2018 · Shiv Krupa Enterprise
Srishti Oasis PH 2 Wing B Sands
declared completion Dec 2023 · Shiv Krupa Enterprise

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026