MahaRERA Property Intelligence · Mumbai City

ST ANTHONY APARTMENT

P51900004642 · MAHIM · promoter Suraj Estate Developers

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP51900004642
Registered on09 Aug 2017
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Suraj Estate Developers is the promoter of record on 54 projects, of which 10 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
ST ANTHONY APARTMENT1G+1031 Mar 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202030 Mar 2020REASON FOR EXTENSION OF DATE OF POSSESSION We had obtained the first IOD vide No. CHE/CTY/1382/GN/337(NEW) dated 05/11/2016 for stilt + 7 storey building. We had amended the pl

Location, Land & Connectivity

Located at MAHIM, MMC CROSS ROAD, Ward GNorth, Mumbai City, 400016. Per the filed land record, the plot is bounded to the north by FP 453, to the south by FP450, to the east by MMC CROSS ROAD NO 2 and to the west by FP 452. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Lower Parel / Worli business district5 km
Chhatrapati Shivaji Int'l Airport6 km
Andheri MIDC / SEEPZ11 km
Powai / Hiranandani business park11 km
Nariman Point / Fort13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Suraj Estate Developers LTD is the promoter on 15 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Suraj Estate Developers LTD project & its RERA track record →

Other flagged projects by Suraj Estate Developers LTD

Suraj Estate Developers LTD
FlaggedMumbai City
Suraj Estate Developers LTD
FlaggedMumbai City
Suraj Estate Developers LTD
FlaggedMumbai City
Suraj Estate Developers LTD
FlaggedMumbai City
Suraj Estate Developers LTD
FlaggedMumbai City
Suraj Estate Developers LTD
FlaggedMumbai City

Other RERA-registered projects in Mahim

Makhdoom Heights
possession by Nov 2026 · Naqi Developers Private Limited
Karpur Heights
possession by Dec 2026 · Parvasha Grihnirman Sanstha
Airyaman Terraces
possession by Dec 2026 · Airyaman Developers LLP
ANJ Ananda
possession by Dec 2026 · A N J Recon LLP
Kapil Tirth
possession by Dec 2026 · Prathamesh Projects LLP
Medius
possession by Dec 2026 · Aventa Properties LLP

Major developers building in Mahim

Other RERA-registered projects in Mumbai City

Stardeous
possession by Dec 2027 · Heston Builders PVT LTD
Stella
declared completion Mar 2019 · Sant Sagar Builders AND Developers Priva
Sterling Luxuria
possession by Jun 2027 · Mohamed Talha Abubakar Momin
Subodh Sagar
possession by Dec 2027 · Subodh Darshan Associates
Sugan Heights
possession by Aug 2026 · Gulabdevi Jain & Others
Sugee Gaurav
possession by Mar 2028 · Sugee Twenty One Developers LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026