Mumbai/Project record

MahaRERA · the public record

SUBODH

Owale · NEW HOMES CORPORATION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

33units filed as unsoldInventory · 13 September 2026
14 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

14 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700005802

Delivery and registration

When is the project declared for completion?

SUBODH is registered with MahaRERA as P51700005802 and the promoter has declared completion for 14 Mar 2024.

14 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700005802
Registered on14 Aug 2017
Promoter-declared completion14 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SUBODH record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 36 homes carry one, and 33 of the 69 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
OFFICE NO 4345 sqftRs 11,372 a sq ft typical, over Rs 8,585 to Rs 14,41918 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SUBODH, 25 of the 33 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 32 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SUBODH1G+831 Mar 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 3 times, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2021Due to Covid 19, Migrant labour are not back in full quorum hence work could not be started in full swing. As 50% of flats are not sold, association or society is not formed so NOC
30 Sep 202115 Mar 2023While registering project it was proposed to acquire adjoining plot and accordingly there was balance FSI in the plot. The same was declared at time of registration. Now with amalg
15 Mar 202314 Mar 2024Due to amendment in plan, we need an extension.

Location, Land & Connectivity

Located at Owale, Thane, Thane, 400615. Per the filed land record, the plot is bounded to the north by ROAD, to the south by HANUMAN TAMPLE, to the east by ROAD and to the west by CHALTA NO 191. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~18 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park18 km
Andheri MIDC / SEEPZ19 km
Chhatrapati Shivaji Int'l Airport23 km
Bandra Kurla Complex (BKC)25 km
Lower Parel / Worli business district34 km
Nariman Point / Fort41 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Owale

ACE Aristo
possession by Oct 2026 · Gaurav Land Corporation
Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Vihang Plaza - A Commecial
possession by Dec 2026 · Vihang Enterprises
Vihang Woods
possession by Dec 2026 · Vihang Enterprises
Ace Enclave
possession by Dec 2026 · Ace Signature Homes LLP
Cascade Avenue Bellagio
possession by Dec 2026 · Aarsh Construction

Major developers building in Owale

Other RERA-registered projects in Thane

Sudam Residency
declared completion Jun 2026 · Saikrupa Developers
Sudama Chhatra
possession by Mar 2029 · Shree Balaji Construction
Sudama Elevate
possession by Dec 2026 · Sudam Zipa Rasal
Sudama Regency Building NO 1, 5
declared completion Oct 2018 · Shree Siddhivinayak Enterprises
Sudama Regency Building NO 2,3,4
declared completion Dec 2024 · Shree Siddhivinayak Enterprises
Sudama Vallabh Wing A,b,c
declared completion Jun 2026 · Pravin Vandravandas Vora

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026