Mumbai/Project record

MahaRERA · the public record

SURYA COOPERATIVE HOUSING SOCIETY LTD

Jogeshwari East · Dipti Home Makers Pvt Ltd

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800018358

Delivery and registration

When is the project declared for completion?

SURYA COOPERATIVE HOUSING SOCIETY LTD is registered with MahaRERA as P51800018358 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800018358
Registered on26 Oct 2018
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SURYA COOPERATIVE HOUSING SOCIETY LTD record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Dipti Home Makers is the promoter of record on 93 projects registered with MahaRERA, 4 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

93projects

registered with MahaRERA

4flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SURYA COOPERATIVE HOUSING SOCIETY LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10.

BuildingWingsFloorsDeclared completion
SURYA COOPERATIVE HOUSING SOCIETY LIMITED1G+10-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Jogeshwari East, Natwar Nagar Road No. 1, Mumbai City, Mumbai City, 400060. Per the filed land record, the plot is bounded to the north by NATWAR NAGAR ROAD NO 1, to the south by NATWAR NAGAR ROAD NO 2, to the east by 9 MTRS ROAD and to the west by PLOT NO 62. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~2 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ2 km
Chhatrapati Shivaji Int'l Airport5 km
Powai / Hiranandani business park6 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Dipti Home Makers Pvt Ltd is the promoter on 8 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Dipti Home Makers Pvt Ltd project & its RERA track record →

Other flagged projects by Dipti Home Makers Pvt Ltd

Dipti Home Makers Pvt Ltd
FlaggedThane
Dipti Home Makers Pvt Ltd
FlaggedThane
Dipti Home Makers Pvt Ltd
FlaggedThane
Dipti Home Makers Pvt Ltd
FlaggedMumbai Suburban
Dipti Home Makers Pvt Ltd
FlaggedMumbai Suburban

Other RERA-registered projects in Jogeshwari East

Prem Builders
possession by Oct 2026 · Prem Builders
Aim Heritage
possession by Dec 2026 · M/s Aim Realtors Private Limited
AIM Paradise
possession by Dec 2026 · S.k. Enterprises
Avant Heritage - III
possession by Dec 2026 · Avant Heritage III Realty Pvt. Ltd.
Devbhoomi
possession by Dec 2026 · Metro Capital
Iifl Centre
Developer in insolvency (NCLT) · possession by Dec 2026 · Spenta Sun City Private Limited

Major developers building in Jogeshwari East

Other RERA-registered projects in Mumbai Suburban

Suryadarshan CHS LTD
declared completion Apr 2024 · H&d Projects
Surylok
possession by Dec 2029 · Not Available
Sushanku Avenue 36
declared completion Dec 2025 · Sushanku Realty Private Limited
Sushanku Avenue 37
possession by Dec 2027 · Sushanku Realty Private Limited
Suvarnatula CHS SAI Adityaraj
declared completion Dec 2025 · Adityaraj Builders AND Developers
Suvidha Pearl
declared completion Oct 2022 · Kalakruti Realtors Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026