8units filed as unsoldInventory · 16 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
114registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000003052

Delivery and registration

When is the project declared for completion?

Surya Kirti Heights and Tower is registered with MahaRERA as P99000003052 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000003052
Registered on04 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Surya Kirti Heights and Tower record 31 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 31 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In Surya Kirti Heights and Tower, ₹16.63 Cr of a declared ₹20.51 Cr estimated project cost is reported as incurred, about 81.0%, as at the last certified filing with MahaRERA.

81.0%

₹16.63 Cr

of ₹20.51 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In Surya Kirti Heights and Tower, 106 of 114 homes filed with MahaRERA are recorded as sold or booked, about 93%, and 8 remain available.

93%sold

106 of 114 homes

₹25.50 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹24.34 Cr (about 95%) is recorded as collected and ₹1.16 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 106 registered agreements, the effective carpet rate is ₹5,795/sqft, with eight in ten falling between ₹3,869 and ₹7,461 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1H-105551 sqft (51.2 sqm)₹31.23 Lakh
Floor 11H-1103384 sqft (35.64 sqm)₹21.74 Lakh
Floor 2H-205551 sqft (51.2 sqm)₹31.23 Lakh
Floor 3H-305551 sqft (51.2 sqm)₹31.23 Lakh
Floor 8B-804530 sqft (49.22 sqm)₹30.02 Lakh
Floor 8H-802418 sqft (38.87 sqm)₹23.71 Lakh
Floor 8H-803384 sqft (35.64 sqm)₹21.74 Lakh
Floor 9H-904384 sqft (35.64 sqm)₹21.74 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 16 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 106 homes carry one, and 8 of the 114 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B-804530 sqftRs 28.08 lakh typical, over Rs 18.29 lakh to Rs 37.10 lakh23 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

In Surya Kirti Heights and Tower, every one of the 8 unsold homes has agreements filed on its own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 7 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 114 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
Surya Kirti heights H wing1G+1267-
Surya Kirti Tower B wing1G+1247-

Unit mix on the filing: 108 residential and 6 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

5 complaints are on the MahaRERA record for Surya Kirti Heights and Tower, with orders passed in 5 of them.

5complaints

5with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000000047930/09/2017SUNIL T FULKAR vs SR SHAH VALA ASSOCIATES.BHIMSEN BAGGA & HITANSHU BAGGAorder passed
CC00600000019690515/05/2021Atul Pravin Shah vs S.R. & SHAH-VALA ASSOCIATESorder passed
CC00600000019341017/07/2020Shahanaj i Shaikh vs BHIMSEN BAGGAorder passed
CC00600000019860810/10/2021Mr Bhimsen Bagga Mr Hitanshu Bagga Partners of S R and Shah Vala Associates vs Mr. Milan Kirtikant Shahorder passed
CC00600000039759709/10/2023SR Shahvala Associates vs Mrs. Mehr Lalit Nihlaniorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019The proposed completion date for our project mentioned while doing the RERA registration was 31st December 2018. We would like to bring up some facts about the project, which hav
31 Dec 201930 Jun 2021The recent pandemic has brought the whole country including the real estate industry to a standstill and due to reverse migration of labourers, the construction work has stopped co
30 Jun 202131 Dec 2025In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various r
31 Dec 202531 Dec 2026We, S R & Shah Vala Associates, the promoter of the project Surya Kirti Heights and Tower (Registration No. P99000003052) under MahaRERA, hereby submit our request for an extensio

Location, Land & Connectivity

Located at Virar, Virar, Vasai, Palghar, 401202. Per the filed land record, the plot is bounded to the north by 9 mtr internal road, to the south by 9 mtr internal road, to the east by 40 m wide D P road and to the west by 12 m wide D P road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~39 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ39 km
Powai / Hiranandani business park41 km
Chhatrapati Shivaji Int'l Airport43 km
Bandra Kurla Complex (BKC)45 km
Lower Parel / Worli business district53 km
Nariman Point / Fort61 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vasai West

Happy Home Jasmine C D
possession by Sep 2026 · Happy Home Corporation
Dream Aura
possession by Dec 2026 · Clement Regency Developers
Vijaya Complex
Not filing quarterly progress reports · possession by Dec 2026 · Padmavati Enterprises
Ashoka Heavens
possession by Dec 2026 · Shree Mahashraman Realtors
Dattani Vertex Building No.4 Wing EF
possession by Dec 2026 · Brijesh Satish Dattani
Gokarna Residency
possession by Dec 2026 · Harshal Anil Acharya

Other RERA-registered projects in Palghar

Suryoday Heights
possession by Dec 2028 · Sunray Realty
Sushila Complex
declared completion Dec 2022 · Hareshwar Jayram Kini
Sushila Complex Building NO. 2
declared completion Dec 2022 · Hareshwar Jayram Kini
SV Paradise
possession by Dec 2029 · Siddhivinayak Infra
Svasa Residency
possession by Dec 2028 · Svasa Developers
Swami Enclave
possession by Oct 2028 · M/s. Om Sai Ram Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026