MahaRERA Property Intelligence · Palghar

SVASA RESIDENCY

P99000079062 · TAL VASAI · promoter Svasa Developers

Certificate SignedDue 31 Dec 2028

Delivery & Registration

MahaRERA registrationP99000079062
Registered on03 Feb 2025
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today29 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 26 homes filed with MahaRERA, 0 are sold/booked and 26 remain available (~0% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Note: the project registers 44 homes in total, but this sold/unsold inventory filing covers only 26 of them — the other 18 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 2203315 sqft (29.26 sqm)₹16.27 Lakh
Floor 3303315 sqft (29.26 sqm)₹16.27 Lakh
Floor 3306315 sqft (29.26 sqm)₹16.27 Lakh
Floor 4403315 sqft (29.26 sqm)₹16.27 Lakh
Floor 4405485 sqft (45.07 sqm)₹25.06 Lakh
Floor 4406315 sqft (29.26 sqm)₹16.27 Lakh
Floor 5501485 sqft (45.07 sqm)₹25.06 Lakh
Floor 5502485 sqft (45.07 sqm)₹25.06 Lakh
Floor 5503315 sqft (29.26 sqm)₹16.27 Lakh
Floor 5504485 sqft (45.07 sqm)₹25.06 Lakh
Floor 5505485 sqft (45.07 sqm)₹25.06 Lakh
Floor 5506315 sqft (29.26 sqm)₹16.27 Lakh
Floor 6601485 sqft (45.07 sqm)₹25.06 Lakh
Floor 6602485 sqft (45.07 sqm)₹25.06 Lakh
Floor 6603315 sqft (29.26 sqm)₹16.27 Lakh
Floor 6604485 sqft (45.07 sqm)₹25.06 Lakh
Floor 6605485 sqft (45.07 sqm)₹25.06 Lakh
Floor 6606315 sqft (29.26 sqm)₹16.27 Lakh
Floor 7701317 sqft (29.43 sqm)₹16.36 Lakh
Floor 7702317 sqft (29.43 sqm)₹16.36 Lakh
Floor 7703315 sqft (29.26 sqm)₹16.27 Lakh
Floor 7704317 sqft (29.43 sqm)₹16.36 Lakh
Floor 7705386 sqft (35.89 sqm)₹19.95 Lakh
Floor 7706315 sqft (29.26 sqm)₹16.27 Lakh
Ground/Floor 0S-1385 sqft (35.77 sqm)₹24.86 Lakh
Ground/Floor 0S-2385 sqft (35.77 sqm)₹24.86 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 44 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING NO 11G+744-

Unit mix on the filing: 42 residential and 2 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at TAL VASAI, VILLAGE NILEMORE, Vasai, Palghar, 401208. Per the filed land record, the plot is bounded to the north by PLOT NO 62, to the south by PLOT NO 60, to the east by PLOT NO 74 and to the west by PLOT NO 24. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Vasai East

Samruddhi Ind. Estate
possession by Jul 2026 · Krisha Buildtech LLP
Armaan Crystal Uptown
possession by Aug 2026 · Armaan Housing LLP
Nakshatra Aarambh
possession by Sep 2026 · JSB Shelters LLP
AAI Chandika Hills
possession by Sep 2026 · Shivam Builders & Developers
Dreams Heights Building NO- I
possession by Sep 2026 · Lodha Builders AND Developers
Trinity Oasis
possession by Sep 2026 · Harsh Tirupati Developers LLP

Major developers building in Vasai East

Other RERA-registered projects in Palghar

Swami Enclave
possession by Oct 2028 · M/s. Om Sai Ram Infra
Swapna Gandha Building No.1
declared completion Sep 2024 · Om Sadguru Developers
Swapna Shilpa Tower
possession by Dec 2028 · Swapna Shilpa Developers
Swapnalok Residency Phase II
declared completion Dec 2024 · Ashapura Builders & Developers
Swapnalok Residency Phase II Riddhi Building Wing B AND C
declared completion Jan 2024 · Dhanesh Chand Patwa
Swapnapurti Complex
possession by Dec 2029 · Yashlaxmi Creations

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026