Mumbai/Project record

MahaRERA · the public record

THARWANI ARIANA PHASE IV

MOUJE · ANIL HARDASMAL THARWANI

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700007834

Delivery and registration

When is the project declared for completion?

THARWANI ARIANA PHASE IV is registered with MahaRERA as P51700007834 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700007834
Registered on18 Aug 2017
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for THARWANI ARIANA PHASE IV record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 28 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Anil Hardasmal Tharwani is the promoter of record on 30 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

30projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for THARWANI ARIANA PHASE IV in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+20.

BuildingWingsFloorsDeclared completion
MELODY1G+20-
NEBULA1G+20-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Chopra Court Ulhasnagar5392015Framing Of Issues
Kalyan332015Framing Of Issues

Location, Land & Connectivity

Located at MOUJE, S NO. 133/1(P) AND 133/2(P), Kalyan, Thane, 421501. Per the filed land record, the plot is bounded to the north by PRAKASH LAXMAN BHOIR LAND, to the south by Ravindra Kanhu Karales Survey No 133 part , to the east by MOUJE VADAVLI LIMITS and to the west by SURVEY NO 133 PART. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~35 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park35 km
Andheri MIDC / SEEPZ38 km
Chhatrapati Shivaji Int'l Airport40 km
Bandra Kurla Complex (BKC)40 km
Lower Parel / Worli business district47 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anil Hardasmal Tharwani is the promoter on 11 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Anil Hardasmal Tharwani project & its RERA track record →

Other flagged projects by Anil Hardasmal Tharwani

Anil Hardasmal Tharwani
FlaggedThane
Anil Hardasmal Tharwani
FlaggedThane
Anil Hardasmal Tharwani
FlaggedThane
Anil Hardasmal Tharwani
FlaggedThane

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Tharwani Ariana Phase IV
declared completion Jun 2026 · Anil Hardasmal Tharwani
Tharwani Majestic Towers Phase I
declared completion Dec 2025 · Anil Hardasmal Tharwani
Tharwani Majestic Towers Phase II
possession by Dec 2026 · Anil Hardasmal Tharwani
Tharwani Millennium Arcade
declared completion Apr 2025 · Tharwani Realtors
Tharwani Millennium City Phase I
declared completion Jul 2023 · Tharwani Realtors
Tharwani Millennium City Phase III
possession by Dec 2026 · Tharwani Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026