MahaRERA Property Intelligence · Thane

THE CLASSIQUE

P51700019813 · DOMBIVLI EAST · promoter Dreamz Developers

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51700019813
Registered on05 Mar 2019
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Dreamz Developers is the promoter of record on 17 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
THE CLASSIQUE1G+2231 Dec 2022

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 0. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1240003205/09/2024Sujit Dhondiram Salunkhe vs DREAMZ DEVELOPERSpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202330 Apr 2024Due to pendamic construction activity affected adversly and even partner looking after project was infected. Now the building is ready and we wish to apply for OC
30 Dec 202330 Sep 2024Our Project is in the ready possession and we have applied for OC however we have not received OC yet, we are also enclosing our ready Building structure photo.

Location, Land & Connectivity

Located at DOMBIVLI EAST, NANDIVALI ROAD, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by SURVEY NO 36, to the south by SURVEY NO 32, to the east by SURVEY NO 34 and to the west by SURVY NO 38. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Premsadan CHS
possession by Jul 2026 · Namrata Realtors
OM Trimurti Darshan
possession by Aug 2026 · Prachi Group
Pannash
possession by Aug 2026 · Technicon
Rashmi Priya CO-OP HSG SOC LTD
possession by Aug 2026 · Shree Riddhi Siddhi Infraproject
Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel

Major developers building in Dombivli East

Other RERA-registered projects in Thane

The Domus
declared completion Dec 2024 · Aramus Realty LLP
THE Domus Prive
possession by Dec 2026 · Aramus Ventures LLP
The Elements
possession by Dec 2031 · TPV Ventures LLP
THE Empress
declared completion Mar 2023 · Unique Shanti Developers LLP
THE Enclave
possession by Dec 2027 · Milestone Constructions
THE Florenza
declared completion Dec 2025 · Priism Infraa

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026